Page 296 - Advances in Renewable Energies and Power Technologies
P. 296

3. Sizing of Hybrid PV/Batteries Bank/Diesel Generator System  269




                  of 20 years, and initial cost of the DG including used fuel cost. These costs are
                  implemented in the following set of equations:

                                                                                (8.17)
                      cost PV ¼ðcost of investement þ 20   cost of maintenanceÞ  N pv
                      cost battery ¼ðcost of investement þ y   cost of investementÞ  N bat  (8.18)

                                        cost DG ¼ C DE þ C oil þ C fuel         (8.19)
                  where y represents the number of battery replacements during 20 years of system
                  operation, C DE is the capital cost of the DG, C oil is the cost of lubricating oil
                  used in the DE, and C fuel is the cost of diesel fuel consumed.

                  3.2.2 Optimization Constraints
                  The following set of constraints is used in the sizing optimization process of the
                  hybrid PV/batteries bank/DG renewable energy system:


                                          7kW   P d   15 kW                     (8.20)
                                             55   N pv   66                     (8.21)
                                             6   N bat   10                     (8.22)

                                                LLP ¼ 0                         (8.23)
                  These ranges give the best performance in the optimization process. The choice of
                  each range affects the conversion of the optimization algorithm and the obtained re-
                  sults. The optimization algorithm was executed many times and the results of each
                  run were used in determining the ranges of each parameter that gives best hybrid en-
                  ergy system size.

                  3.2.3 Methodology
                  PSO algorithm is used to optimally size the hybrid PV/batteries bank/DG renewable
                  energy system. The optimization process is achieved for both minimum overall sys-
                  tem cost and pollution criteria. Typically, PSO algorithms do not always guarantee
                  optimal solution. In fact, achieving algorithm conversion and optimal solution de-
                  pends mainly on the chosen range of each part used in the hybrid system. In addition,
                  the final achieved solution depends on the used optimization strategy for the hybrid
                  system.
                     The strategy used in the optimization process consists of three phases. The first
                  phase is introduced to size both the PV panels array that supplies the load during the
                  daytime and the batteries bank that supplies the load when produced PV power is not
                  sufficient to meets the load needs especially during sunset and sunrise. In this step,
                  the optimal numbers of PV panels and batteries are found. Typically, the number of
                  PV panels should be maximized, while the number of batteries should be minimized
   291   292   293   294   295   296   297   298   299   300   301