3. Energy Management for Photovoltaic Installations  365






                                           P Renew, P load, SOC min, SOC maxP pv,
                                           P load, SOC min, SOC max



                                              Calculate  P=P Renew-P load



                                       No                    Yes
                                                  P  0


                                                         No                  Yes
                              SOC>SOC min
                                                                SOC<SOC max
                          No           Yes



                      Mode 5
                                         P Renew=0
                                          P pv=0         Mode 4            Mode 1
                                  No
                                               Yes

                                   Mode 2      Mode 3

                  FIGURE 11.9
                  Energy management strategy of PV/wind system with battery storage.

                     The different modes depend on the three switches K 1 ,K 2 , and K 3 . Mathemati-
                  cally, it results in eight cases (Table 11.14).
                     After simplification, we obtain the Table 11.15:
                     But only five cases can be exploitable as real cases (Table 11.16)
                     The different powers can be expressed in terms of the different switches as:

                                P Renew ¼ K 1 $K 2 $K 3 þ K 1 $K 2 $K 3 þ K 1 $K 2 $K 3  (11.27)
                                      P batt ¼ K 1 $K 2 $K 3 þ K 1 $K 2 $K 3   (11.28)
                     These equations can be minimized to:

                                            P Renew ¼ K 2 þ K 1                (11.29)
                                               P batt ¼ K 3                    (11.30)
                     Therefore, the load power is given as:
                                    P load ¼ðK 2 þ K 1 Þ$P Renew þ K 3 $P batt  (11.31)