Page 235 - Air Pollution Control Engineering
P. 235

05_chap_wang.qxd  05/05/2004  3:46 pm  Page 214
                    214                                                    Lawrence K. Wang et al.

                    Table 6
                    Capital Costs Factors for Absorbers
                    Cost Item                                                     Factor
                    Direct Costs (DC)
                    Purchased equipment cost
                       Absorber (tower & packing) + auxillary  equipment       As estimated, EC
                       Instrumentation                                                 0.10 EC
                       Sales tax                                                       0.03 EC
                       Freight                                                         0.05 EC
                         Purchased Equipment Cost (PEC)                        1 PEC = 1.18 EC
                    Direct Installation Costs
                       Foundation and supports                                       0.12 PEC
                       Erection and handling                                         0.40 PEC
                       Electrical                                                    0.01 PEC
                       Piping                                                        0.30 PEC
                       Insulation                                                    0.01 PEC
                       Painting                                                      0.01 PEC
                         Direct Installation Cost                                    0.85 PEC
                    Site preparation                                            As required. SP
                    Building                                                  As required, Bldg.
                         Total Direct Costs                                1.85 PEC + SP + Bldg.
                    Indirect Costs (IC)
                       Engineering                                                   0.10 PEC
                       Construction                                                  0.10 PEC
                       Contractor fee                                                 0.10PEC
                       Start–up                                                      0.01 PEC
                       Performance test                                              0.01 PEC
                       Contingencies                                                 0.03 PEC
                         Total Indirect Cost                                         0.35 PEC
                    Total Capital Costs                                    2.20 PEC + SP + Bldg.
                       Source: ref. 9.





                    scrubber tower treating 50,000 scfm with a pressure loss of 5 in. of H O, the fan is pulling
                                                                               2
                    approx 46 hp. This horsepower is costing the plant over $37,000 per year. Therefore, if
                    a 50% reduction in pressure drop in the tower could be realized, the plant would net a
                    power savings of over $18,000 per year.
                       Another consideration in scrubber tower operating cost is the cost of scrubbing liquor
                    (absorbent), usually water that is consumed in normal operation of the tower. The annual
                    solvent required (ASR) is expressed by
                                                  ASR = 60 (L ) HRS                           (26)
                                                            gal
                       Table 6 presents capital cost factors for several absorbents (9). The annual solvent cost
                    (ASC) may now be calculated by multiplication of ASR by the unit solvent cost (USC):
                                                  ASC = (USC) (ASR)                           (27)
   230   231   232   233   234   235   236   237   238   239   240