Page 257 - Air Pollution Control Engineering
P. 257

05_chap_wang.qxd  05/05/2004  3:46 pm  Page 236
                    236                                                    Lawrence K. Wang et al.

                                        2
                          L'' = 1612 lb/h-ft (Example 7)
                                                          2
                          3600G    = (3600)(0.34) = 1224 lb/h-ft (Example 7)
                                area
                                       3
                          D = 0.071 lb/ft (Example 5)
                            G
                                       3
                          D = 62.18 lb/ft at 85°F (Example 5)
                            L
                       Substituting these values into Eq. (21) to determine pressure drop (P ):
                                                                              a
                                                         2
                          P = (g × 10 −8  [10 (r L"/D )  ) /D                              (21)
                                             L ] (3600G
                           a                          area  G
                                                                   2
                                        −8
                          P = (11.13 × 10 ) [10  (0.00295)(1612 ) / 62.18 ] (1224) / 0.071
                           a
                                        −8
                          P = (11.13 × 10 ) [10  (0.07648) ] (1,498,176) / 0.071
                           a
                                        −8
                          P = (11.13 × 10 ) [1.1926] (1,498,176) / 0.071
                           a
                                      2
                          P = 2.78 lb/ft -ft
                           a
                       The total pressure drop through a packed tower or wet scrubber can then be calculated:
                          Ht     = 23 ft (from Example 7)
                            column
                          P    = P Ht                                                      (22)
                           total  a  column
                          P    = (2.8)(23) = 64.4 lb/ft 2
                           total
                          P    /5.2 = 12.4 in. H O
                           total            2
                    Example 10
                       In this exercise, the initial (capital) costs and operating costs of a wet scrubber are esti-
                       mated. These costs include initial cost of purchase as well as direct and indirect annual
                       costs (or total annual costs). Recovery credit is assumed to be negligible.
                       Solution
                       A. Total Cost of Absorption (Wet Scrubber) Systems
                          The cost of the absorption system can be found in Figure 7. The cost of packing
                          required to fill the tower is estimated using Table 2 with the volume of packing deter-
                          mined in the previous discussion. Likewise, secondary costs for related equipment
                          were also previously determined. Summation of these costs will determine the total
                          capital outlay needed for this wet scrubber.
                          1. Absorber tower cost = $
                          2. Packing cost = $
                          3. Auxiliary equipment cost = $
                          4. Equipment cost (EC) = 1 + 2 + 3 = $
                          The purchased equipment cost, PEC, is obtained from the equipment cost determined
                          above and the factors found in Table 6.
                             PEC = EC + instrumentation + taxes + freight charges
                             PEC = $
                          Total capital cost (TCC) is estimated using the above calculated PEC and the factors
                          found in Table 6.
                             TCC = 2.20PEC + SP + building cost
                             TCC = $
                             where SP is the site preparation cost ($).

                       B. Direct Annual Cost of a Wet Scrubber System (Absorber)
                          The total annual costs of a scrubber system include direct costs of power, solvent
                          (absorbent), labor, and so form. Additionally, indirect costs such as taxes, administra-
                          tive costs, insurance, and so on. must also be considered to fully appreciate the total
                          capital demanded to operate a scrubber system for a full year.
   252   253   254   255   256   257   258   259   260   261   262