322 CHAPTER 7 TRANSPORTATION, ASSIGNMENT AND TRANSSHIPMENT PROBLEMS
Table 7.33 Production, Demand and Cost Estimates for Contois Carpets
Production Demand Production Inventory
Capacity (square Cost (E/ Cost (E/
Quarter (square metres) metres) square metre) square metre)
1 600 400 2 0.25
2 300 500 5 0.25
3 500 400 3 0.25
4 400 400 3 0.25
Figure 7.12 Network Representation of the Contois Carpets Problem
Production Demand
Nodes Nodes
1 5
600 Quarter 1 2 Quarter 1 400
Production Demand
0.25
2 6
300 Quarter 2 5 Quarter 2 500
Production Demand
0.25
3 7
500 Quarter 3 3 Quarter 3 400
Production Demand
0.25
4 8
400 Quarter 4 3 Quarter 4 400
Production Demand
Production Production Demands
Capacities (arcs)
The objective is to determine a production scheduling and inventory policy that
will minimize the total production and inventory cost for the four quarters. Con-
straints involve production capacity and demand in each quarter. As usual, a linear