Page 114 - Analysis, Synthesis and Design of Chemical Processes, Third Edition
P. 114

cost benefit of recycling the raw materials would far outweigh the cost of the additional tank. Third, it is
                    observed that, overall, only 60% of the product made in the reactor is crystallized out in Step 5. This
                    means that the mother liquor (solution containing product to be crystallized after some has crystallized
                    out)  contains  significant  amounts  of  valuable  product.  Additional  crystallization  steps  could  recover
                    some, if not most, of the valuable product. The strategy for accomplishing this could be as simple as
                    scheduling a second or third cooling or crystallization step, or it could involve storing the mother liquor
                    from several batch processes until a sufficient volume is available for another cooling or crystallization
                    step. These additional crystallization steps are tantamount to adding additional separation stages.



                    3.2 Gantt Charts and Scheduling




                    Gantt charts (see, for example, Dewar [3]) are tabular representations used to illustrate a series of tasks
                    (rows) that occur over a period of time (columns). These charts graphically represent completion dates,

                    milestone achievements, current progress, and so on [3]  and  are  discussed  further  in Chapter  26  as  a
                    planning tool for completing large design projects. In this chapter, a simplified Gantt chart is used to
                    represent the scheduling of equipment needed to produce a given batch product. Example 3.2 illustrates
                    the use of Gantt charts to show the movement of material as it passes through several pieces of equipment
                    during a batch operation.


                    Example 3.2


                    Draw a Gantt chart that illustrates the sequence of events in the production of the API in Example 3.1.



                    Solution




                    Gantt charts for this process are shown in Figure E3.2. Note that in both charts, Steps 1 and 2 have been
                    consolidated into one operation because they occur sequentially in the same piece of equipment. The top

                    chart shows the row names as tasks, and the bottom figure simply identifies each row with the equipment
                    number. In general, the notation used in the bottom figure will be adopted.


                    Figure E3.2 Gantt Chart Showing Sequence of Events for the Manufacture of API in Example 3.1
   109   110   111   112   113   114   115   116   117   118   119