Page 116 - Analysis, Synthesis and Design of Chemical Processes, Third Edition
P. 116

(3.1)










                    where T        is  the  total  time  to  process n  batches  without  overlapping,  each  batch  having m  steps  of
                              NO
                    duration t  t , ... , t . For this example, the total time is equal to (8)(3.5 + 0.5 + 3.5 + 2 + 4.0 + 1.0) = (8)
                               1, 2
                                          m
                    (14.5) = 116.0 h.

                    For  the  process  described  in Figure  3.1,  using  the  nonoverlapping  scheme,  the  equipment  is  used
                    infrequently, and the total processing time is unduly long. However, such a scheme might be employed in
                    plants that operate only a single shift per day. In such cases, the production of a single batch might be

                    tailored to fit an 8 or 10 h shift (for this example, the shift would have to be 14.5 h), with the limitation
                    that  only  one  batch  would  be  produced  per  day. Although  such  a  scheme  does  not  appear  to  be  very
                    efficient,  it  eliminates  prolonged  storage  of  intermediate  product  and  certainly  makes  the  scheduling
                    problem easy.


                    The total time to process all the batches can be reduced by starting a batch before the preceding batch has
                    finished.  This  is  equivalent  to  shifting  backward  the  time  blocks  representing  the  steps  in  the  batch
                    process, as shown in Figure 3.2.


                    Figure 3.2 Backward Shifting of Batches, Giving Rise to Overlapping Sequencing























                    This shifting of batches backward in time leads to the concept of overlapping sequencing of batches. The
                    limit of this shifting or overlapping process occurs when two time blocks in consecutive batches just
                    touch each other (assuming that cleaning, inspection, and charging times are included). This situation is
                    shown in Figure 3.3.


                    Figure 3.3 The Limiting Case for Overlapping Batch Sequencing
   111   112   113   114   115   116   117   118   119   120   121