Page 301 - Analysis, Synthesis and Design of Chemical Processes, Third Edition
P. 301

account the time value of money that is necessary for a thorough measure of profitability. The effects of
                    the time value of money on profitability are considered in the next section.


                    10.2.2 Discounted Profitability Criteria





                    The main difference between the nondiscounted and discounted criteria is that for the latter we discount
                    each of the yearly cash flows back to time zero. The resulting discounted cumulative cash flow diagram is
                    then used to evaluate profitability. The three different types of criteria are:


                    Time  Criterion.      The discounted  payback  period  (DPBP)  is  defined  in  a  manner  similar  to  the
                    nondiscounted version given above.


                              Time required, after start-up, to recover the fixed capital investment, FCI , required for the
                    DPBP =                                                                                        L
                              project, with all cash flows discounted back to time zero



                    The project with the shortest discounted payback period is the most desirable.

                    Cash Criterion.   The discounted cumulative cash position, more commonly known as the net present

                    value (NPV) or net present worth (NPW) of the project, is defined as
                          NPV = Cumulative discounted cash position at the end of the project

                    Again,  the NPV of a project is greatly influenced by the level of fixed capital investment, and a better

                    criterion  for  comparison  of  projects  with  different  investment  levels  may  be  the present  value  ratio
                    (PVR):








                    A present value ratio of unity for a project represents a break-even situation. Values greater than unity
                    indicate profitable processes, whereas those less than unity represent unprofitable projects. Example 10.2

                    continues Example 10.1 using discounted profitability criteria.

                    Example 10.2



                    For the project described in Example 10.1, determine the following discounted profitability criteria:
                          a.   Discounted payback period (DPBP)
                          b.   Net present value (NPV)
                          c.   Present value ratio (PVR)


                    Assume a discount rate of 0.1 (10% p.a.).


                    The procedure used is similar to the one used for the nondiscounted evaluation shown in Example 10.1.
                    The discounted cash flows replace actual cash flows. For the discounted case, we must first discount all
                    the  cash  flows  in Table E10.1  back  to  the  beginning  of  the  project  (time  =  0).  We  do  this  simply  by
   296   297   298   299   300   301   302   303   304   305   306