Page 34 -
P. 34

be much more likely to occur and, if they do occur, they might cause much more damage
                          than others. In those cases, steps should be taken to hedge the project (or portfolio)
                          against the risk; this is usually referred to as “mitigation” when it is done in the context of
                          project planning.
                          Risk planning for most projects can be done in one meeting, usually in less than two
                          hours. The meeting is led by the project manager, who should select a team similar (or
                          identical) to that of the Wideband Delphi session (see Chapter 3), with the exception that
                          there is no moderator. Table 2-2 contains a script for creating the risk plan.

                          TABLE 2-2. Risk planning script
                           Name           Risk planning script
                           Purpose        To assess risks and create a risk plan.
                           Summary        The risk planning meeting happens in three parts: a brainstorming session to identify risks; a
                                          discussion in which the probability and impact of each risk is estimated; and a discussion to
                                          identify actions that can mitigate risks. The end result is a risk management plan, which
                                          should be included verbatim in the final project plan.
                           Work Products  Input
                                            Any project documentation that has been developed so far.
                                          Output
                                            Risk plan.
                                            Assumptions generated by the Delphi process.
                                            Assumptions in the vision and scope document.
                           Entry Criteria  The project manager has gathered the project team for a two-hour meeting to assess the
                                          project’s risks.
                           Basic Course of Events  1. Brainstorm potential risks. The project manager leads a brainstorming session to identify
                                            risks. Team members suggest every risk they can think of; the project manager writes the
                                            risks on a whiteboard as they come up. Brainstorming should be reminiscent of microwave
                                            popcorn: a few ideas should “pop” at first, followed by a large number being fired rapidly,
                                            slowing down to a final few “pops.” The team will generally be able to judge when the risk
                                            identification is over.
                                          2. Estimate the impact of each risk. The team assigns a number from 1 (highly unlikely) to 5
                                            (very likely to occur) to represent the estimated probability of each risk. Similarly, impact
                                            should be estimated by assigning a number from 1 (for a risk with low impact) to 5 (for a
                                            risk which, if it occurs, will require an enormous effort to clean up).
                                          3. Build the risk plan. The team identifies actions to be taken to mitigate high-priority risks

                                            and creates a risk plan that documents these actions.
                           Exit Criteria  The risk plan is finished.

                          Brainstorm potential risks
                          Risks should be as specific as possible. It’s true that “The project might be delayed” or “We
                          will go out of business” are risks; however, they are far too vague to do anything about.
                          When a vague risk comes up, the project manager should prod the team into making it
                          more specific. What are the possible sources of the project delay? How have past projects
                          been delayed? For example, if the last project was late because a major stakeholder quit
                          and was replaced by someone who disagreed with his predecessor’s vision, the team
                          should write that down as a risk. The assumptions documented in the vision and scope


                   26  CHAPTER TWO
   29   30   31   32   33   34   35   36   37   38   39