Risk plan for project  Call center application project
                            Assessment team members Mike, Barbara, Quentin, Jill, Sophie, Dean, Kyle
                            Risk                    Prob. Impact Priority Actions
                            Senior management will move call  3  5  15  1. Mike will add a requirements task to the
                            center offshore, which will require an  schedule for Quentin to begin investigating
                            internationalization feature to be built  internationalization requirements.
                                                                    2. If the call cener is moved, Mike will call
                                                                    a team meeting to review the schedule
                                                                    and Barbara will inform the rest of senior
                                                                    management of the potential delay.
                            Jim will be pulled off of this project for 4  3  12  1. Assign Kyle to work with Jill on the initial
                            Royalty Archive project bug fixes       programming tasks to make sure he is
                                                                    cross-trained.
                                                                    2. If Jill is pulled off, she will spend 10% of
                                                                    her time reviewing this project with Kyle.
                            Reporting feature will be needed  2  4  8  If this happens, Mike will work with Sophie
                                                                    and Kyle to reestimate the programming tasks.
                            Additional time will be needed to  5  1  5  None
                            gather requirements from potential
                            users at Boston client
                            Will need to support tie-in to support  1  3  3  None
                            additional database vendors


                          FIGURE 2-1. Sample risk plan

                            Are there any resources known to be assigned to other projects at the same time that
                            they are assigned to this one?
                            Have dates that the resources are unavailable (scheduled downtime for machines, vaca-
                            tions for people, times that facilities cannot be booked, etc.) been taken into account?
                          Project schedule
                            Does the project plan include a schedule?
                            Are there any tasks that are missing or incorrect?
                            If a WBS was generated by a Delphi session, does the project schedule reflect all of the
                            tasks that were identified by the team?

                            Does each task have a predecessor?

                            Is a resource allocated to each task?
                            If multiple resources have been assigned to a single task, has the task’s duration been
                            updated properly to reflect that?

                            Is there a more efficient way to allocate resources?
                            Does the project schedule contain periodic reviews?
                          Risk plan
                            Does the project plan include a risk plan?

                            Are there any risks that are not in the plan?
                            Are there any assumptions (from the vision and scope document or a Delphi session)
                            that represent risks that should be included in the plan?