Page 129 - Beyond Decommissioning
P. 129

110                                                Beyond Decommissioning


          Table 5.1 Continued
                                          buildings, there is  achieved through
                                          further economic  consolidation of spent
                                          benefit of reduced  fuel into a single area.
                                          cost of demolition,  Regarding remaining
                                          but the additional  buildings, there is
                                          cost to maintain  further economic
                                          these buildings  benefit of reduced cost
                                          safe should be   of demolition, but the
                                          considered. The  additional cost to
                                          major incentive to  maintain these
                                          pursuing this    buildings safe should be
                                          option is to reuse  considered. The major
                                          the buildings for  incentive to pursuing
                                          nonnuclear       this option is to convert
                                          purposes.        facilities and buildings
                                                           for new nuclear
                                                           applications or
                                                           nonnuclear applications
                                                           compatible with
                                                           residual radioactive
                                                           levels


            More recently, NRC stated that licensees at decommissioning NRC-licensed facil-
         ities could use “more realistic scenarios” for calculating doses for site release. Such
         scenarios must be based on the “reasonably foreseeable land use” (RFLU) for the
         facility, once decommissioned. NRC suggested that “reasonable foreseeable” means
         reasonable use up to 100 years after site release. In one case, the Kiski Valley Pollution
         Control Authority site in Vandergrift, PA., NRC approved that no further
         decommissioning action should be taken, based on a dose assessment including a
         range of RFLU scenarios.
            Two intermediate cases somewhere between restricted and unrestricted release are
         presented in US Nuclear Regulatory Commission (2006). In fact, the NRC report
         highlights the benefits of using realistic scenarios to demonstrate compliance with
         unrestricted release requirements.


             Two good examples of the use of realistic scenarios are the Nuclear Fuel Services
             (NFS) site in Erwin, TN and the FMRI, Inc (Fansteel) site in Muskogee, OK. The
             NFS staff combined two realistic scenarios to determine radionuclide-specific
             Derived Concentration Guideline Levels (DCGLs, in IAEA terminology: clearance
             levels or criteria). The licensee demonstrated that the shallow, contaminated ground-
             water would not be used as a drinking water source in any case. The licensee then
             demonstrated that the most likely use of the site at license termination was as indus-
             trial site. It also acknowledged that there was considerable suburban development in
             the area. The licensee performed dose calculations for the facility using an industrial
             scenario, as well as a suburban resident scenario. The licensee then chose the lower
   124   125   126   127   128   129   130   131   132   133   134