Page 215 - Boiler_Operators_Handbook,_Second_Edition
P. 215

200                                                                               Boiler Operator’s Handbook


               were used and a few of them were on my projects where,  ple were injured (including me) and others were killed
               despite the drawings specifically listing the requirements,  because we didn’t have those regulations. Follow them
               the steamfitters used the wrong bolts or nuts.       religiously, they are there to protect you and keep you
                    I’m very grateful none of those incidents had a re-  alive. Second, it is the operator’s responsibility to ensure
               sult like using the wrong nuts on the Iwo Jima, a Navy  all those regulations are followed and, more importantly,
               aircraft carrier, in October of 1990 when ten people were  to be the person in charge of lock-out, tag-out.
               killed because a valve bonnet blew off in a confined en-     Don’t be too quick to allow that responsibility
                         5
               gine room.  A valve’s bonnet is that portion of the valve  to reside in someone else, you’ll regret it the day the
               that’s removable without dismantling the attached pip-  contractor’s crew closes and locks out the wrong valve
               ing to provide access to the valve’s internals.      (like on the plant’s only water line) then go out to lunch!
                    Something that sounds good or looks right isn’t the  You’re also the only one in the plant I would count on to
               answer. If you don’t understand a specification or can’t  know every valve that has to be closed to ensure a sys-
               determine whether the material you have complies with  tem or vessel is really isolated. Another problem is that
               it you should consult someone to ensure you have the  the owner of a plant is responsible for the safety of the
               right material.                                      contractors because any hazard in the plant involves the
                    Don’t take the salesman’s word for it because he  property of the owner. If the boss says “let the contractor
               can deny telling you after the catastrophe occurs so  do it” you might point out to him that the contractor can
               you end up holding the bag. Sometimes the mistake is  do it wrong, sue the owner when someone’s injured, and
               immediately evident. I can still remember the look on  the contractor will win!
               a contractor’s face when they started filling a piping   The regulations for lock-out, tag-out are in OSHA
               system that took over a week for five men to install and  29CFR part 1910. They are still changing and evolving
               water was spurting from the longitudinal seam of every  so I don’t intend to address them all here. You should
               piece of pipe. Nobody checked the material, it was all  obtain a copy of that document and be aware of updates.
               “untested” pipe; manufactured for structural use.    You’ll have it to review every time you have to prepare
                    Sometimes you find out later, that’s almost always  a system for maintenance. Right now there are many
               the case when the material isn’t capable of withstand-  methods for satisfying the requirements but one simple
               ing corrosive action of the liquids it contains. I can still  program shown to me by Ken Donithan of Total Boiler
               remember the condition of a mild steel thermometer  Control seems to be a really clean and simple approach
               well we had knowingly installed in a stainless steel  that satisfies the requirements with a minimum of pa-
               piping system because the owner wanted the system  perwork and a great degree of understanding. It’s dem-
               running and we didn’t have time to get a replacement  onstrated in Figure 6-2 which was prepared for work on
               well. We got to replace the well with one of the right  a steam boiler.
               material a week later and discovered there wasn’t much     A diagram or schematic of the system is prepared
               left of that mild steel. Had the plant run for a few more  and laminated with plastic to serve as the key element
               days the well would have corroded away, the thermom-
               eter would have blown out and highly corrosive liquid
               would have been spraying into the plant.
                    There’s one other thing about materials that needs
               to be addressed. You may find that a modern material
               does a better job, something like graphite gaskets for
               cast iron boilers instead of rubber ones. Refer to the sec-
               tion on replacements that follows.



               LOCK-OUT, TAG-OUT

                    First of all I want to say that I’m not one of those
               people that gripes about all the hassle associated with
               lock-out and tag-out regulations and requirements. I op-
               erated in the times before those regulations and have very
               vivid and unsettling recollections of incidents where peo-   Figure 6-2. Lock-out/tag-out diagram
   210   211   212   213   214   215   216   217   218   219   220