Page 238 - Boiler_Operators_Handbook,_Second_Edition
P. 238

Maintenance                                                                                         223


               buy the product at his low prices. He was told thanks,  The tack welds should all be checked to be sure none of
               but no thanks and I’ve been very conscious of what I was  them are cracked; a light tap with a hammer will nor-
               buying thereafter. As far as I’m concerned any pipe that  mally produce a ringing sound, any static is indicative
               goes into a boiler room should have a stencil running  of a crack that can’t be seen without magnification or
               repeatedly along its length that begins “ANSI” and for  other testing. Some procedures require the tack welds
               B31.1 piping also “ASME” followed by a specification  be replaced as the root pass is made but the tacks are
               number and other data including a heat number which  normally incorporated into the root pass.
               makes the material traceable to the piping manufacturer.
               Pipe fittings and valves must bear certain markings but
               certificates aren’t required. They should, however, bear
               a marking that identifies the manufacturer and the ap-
               propriate ANSI specification.
                    As for the welder, the only way to determine the
               quality without requiring RT (radiation testing, fre-
               quently called X-ray) is visual examination by someone
               who knows what to look for. Here’s what to look for:


               Fit-up
                    The fit-up consists of matching the joint between
               two pieces of pipe or a pipe and fitting or weld end
               valve and attaching them with tack welds at no fewer
               than four points evenly spaced around the pipe. The
               two ends should be ground clean to gray metal (no rust,
               paint, oil or other coating) for at least one-half inch from
                                                                         Figure 6-13. Tee showing beveled end prep
               the surfaces to be welded. The pipe should aligned such
               that any differences in the inside edge of each pipe is
               less than 1/16 inch (less for very high pressures and
               temperatures). The joint should also be prepared in a
               manner that conforms with the WPS (Welding Proce-
               dure Specification) which the welder should be able to
               show to you. Typically the ends of the pipe or fitting is
               ground to a bevel as shown in Figure 6-13. That’s the
               standard  preparation  for  an  open  butt  welded  joint
               where the two ends of the pipe are positioned so a cross
               section of the fit-up joint would look like that in Figure
               6-14. Four tack welds are typically used and located at
               quarter points straddling the vertical and horizontal
               centerlines. A keyhole is formed at the end of each tack
               weld providing a starting point for the rest of the root      Figure 6-14. Cross section of fit-up
               pass. This arrangement permits the welder to fill in be-
               tween the two ends to provide a complete weld like the
               cross-section diagram in Figure 6-17. A section through
               a weld wouldn’t look like that because you shouldn’t
               be able to see the black outlines shown in Figure 6-17.
               That’s because the pipe and weld metal should be fused
               together so you can’t tell them apart. The joint should
               be inspected by someone other than those preparing
               the joint and should incorporate use of the gage shown
               in Figure 6-15a to check for the appropriate bevel and
               internal alignment. Figure 6-15b shows use of the gage
               to check for internal misalignment and a proper bevel.       Figure 6-15a. Welding inspection gage
   233   234   235   236   237   238   239   240   241   242   243