Page 249 - Bridge and Highway Structure Rehabilitation and Repair
P. 249

224            SECTION 2                                        STRENGTHENING AND REPAIR WORK



























                        Figure 5.22  Stage concrete deck construction for long spans (density of wet concrete 3 160 pcf).
                        4. The following combinations are added to AASHTO LRFD bridge design code:
                            For strength I condition use
                            •   All dead load of bridge components 4 wet concrete symmetric or unsymmetric pours
                             (DC1)
                            •  Utilities (DC2)
                            •   Construction equipment (CE1)
                            •   Construction material such as screed (CE2)
                            •   Construction live load, such as moving trolleys and deck finishing machines (CLL).

                                3 0.9 to 1.25
                               p
                        5. General dtrength 1 construction live load combination is:
                              (DC1 4 DC2) 4 1.5 (CE1 4 CE2) 4 1.5 (CLL).
                             p
                            •   Stage 1 symmetric pattern of deck pour is assumed.
                              (DC1  pour-1  4 DC2) 4 1.5 (CE1 4 CE2) 4 1.5 (CLL)
                             p
                            •   Stage 2 symmetric pattern of deck pour is assumed.
                              (DC1  pour-2  4 DC2) 4 1.5 (CE1 4 CE2) 4 1.5 (CLL)
                             p
                            •   Stage 3 symmetric pattern of deck pour is assumed as shown in Figure 5.22.
                              (DC1  pour-3  4 DC2) 4 1.5 (CE1 4 CE2) 4 1.5 (CLL)
                             p
                        6. Alternate non-symmetric deck pour:
                            Nonsymmetric pattern of deck pour is assumed. Pattern to be provided by contractor and
                            will vary for each project.
                              ( DC1 nonsym pour  4 DC2) 4 1.5 (CE1 4 CE2) 4 1.5 (CLL)
                             p
                        7. For strength III condition, use wind on superstructure including forming:
                            General construction wind load combination: Wind on superstructure (WS)
                               (DC1 4 DC2) 4 1.5 (CE1 4 CE2) 4 1.4 (WS)
                             p
                            •   Stage 1 symmetric pattern of deck pour is assumed.
                              (DC1     4 DC2) 4 1.5 (CE1 4 CE2) 4 1.4 (WS)
                             p     pour-1
                            •   Stage 2 symmetric pattern of deck pour is assumed.
                              (DC1     4 DC2) 4 1.5 (CE1 4 CE2) 4 1.4 (WS)
                             p     pour-2
                            •   Stage 3 symmetric pattern of deck pour is assumed.
                              (DC1     4 DC2) 4 1.5 (CE1 4 CE2) 4 1.4 (WS)
                             p    pour-3