Page 294 - Chemical engineering design
P. 294

COSTING AND PROJECT EVALUATION
                   Total purchase cost of major equipment items (PCE)
                                         Absorption column        29,000                  269
                                         Recovery column          64,000
                                         Reboiler                   8000
                                         Condenser                  6000
                                         Cooler                     3000
                                         Solvent tank             10,000
                                         Product tank             10,000
                                                     Total      £130,000

                   Estimation of fixed capital cost, reference Table 6.1, fluids processing plant:
                                      PCE £130,000
                                      f 1 Equipment erection  0.40
                                      f 2 Piping            0.70
                                      f 3 Instrumentation   0.20
                                      f 4 Electrical        0.10
                                      f 5 Buildings         none required
                                      f 6 Utilities         not applicable
                                      f 7 Storages          provided in PCE
                                      f 8 Site development  not applicable
                                      f 9 Ancillary buildings  none required
                   Total physical plant cost  PPC  D 132,300 1 C 0.4 C 0.7 C 0.2 C 0.1  D £317,520

                     f 10 Design and Engineering  0.30
                     f 11 Contractor’s Fee      none (unlikely to be used for a small, plant project)
                     f 12 Contingencies         0.10
                   Fixed capital D 317,520 1 C 0.3 C 0.1  D 44,528 round up to £445,000

                   Working capital, allow 5% of fixed capital to cover the cost of the initial solvent charge D
                   445,000 ð 0.05 D £22,250.
                   Total investment required for project D 445,000 C 22,250 D 467,250, say £468,000

                   Annual operating costs, reference Table 6.6:
                   Operating time, allowing for plant attainment D 365 ð 0.95 D 347 d/y, 347 ð 24 D
                   8328 h/y.

                   Variable costs:
                     1. Raw materials, solvent make-up D 10 ð 347 ð 400/1000 D      £ 1388
                     2. Miscellaneous materials, 10% of maintenance cost (item 5) D  £ 2200
                     3. Utilities, cost from Table 6.5:
                        Steam, at 7£/t D 7 ð 8328 ð 200/1000 D                     £11,659
                        Cooling water, at 1.5 p/t D  1.5/100  ð 8328 ð 5000/1000 D  £ 625
                        Power, at 1.2 p/MJ D  1.2/100  ð 360 ð 347 D                £ 1499
                     4. Shipping and packaging                                not applicable
                                                                     Variable costs D £17,371
   289   290   291   292   293   294   295   296   297   298   299