Page 297 - Chemical process engineering design and economics
P. 297

276                                                      Chapter 6





                                                              Vent








                                               -Vortex Breaker







            Figure 6.3  An accumulator.






           Table 6.5  Summary of Equations for Sizing Accumulators

            Subscripts: L = liquid — HV = vessel head


           V = 2V L 't s                                               (6.5.1)
           ts = 5 to  10 min                                           (6.5.2)

                  2
               7tD L
           V = -                                                       (6.5.3)


           L/D = 2.5 to 6                                              (6.5.4)

           f m  = 0.1309  —  for a 2:1 ellipsoidal head, or            (6.5.5)
           fnv =  0.0778  —  for a torispherical head

           Unknowns
           ts, D, L, P, V,  fnv









         Copyright © 2003 by Taylor & Francis Group LLC