10.30   CHAPTER TEN















































                                    FIGURE 10.29 Building envelope detailing.


                         Weathering of exposed envelope systems creates movement in all materials, and
                      allowances must provide for this movement. Movement above-grade is created by several
                      phenomena, as summarized in Table 10.2.
                         To provide for this movement and volume change, control and expansion joints must be
                      designed and placed where such movement is expected. Among the envelope locations for
                      placement of control joints are these:

                      ● Changes in materials
                      ● Changes in plane
                      ● Material volumetric expansion
                      ● Construction joints
                      ● Junction of facade materials to structural components