Page 71 - Design of Simple and Robust Process Plants
P. 71

3.3 Design Philosophies  55
                 Summary
                   .  JIP is a concept to minimize storage, and is based on quality production and
                      supply chain optimization.
                   .  JIP aims to minimize the stored products to base components, and supply
                      additives during loading or at the customer's location.
                   .  Design of storage capacity at the plants and at the customer's location is
                      based on processing reliability, transportation frequency cargo size and relia-
                      bility, and customer delivery requirements.
                   .  The methodology is available for the optimization of design and operation
                      based on Monte Carlo simulations.


                 3.3.10
                 Design for Total Quality Control (TQC)

                 3.3.10.1  Prevent versus cure
                The concept of JIP can only be applied if we are able consistently to produce at speci-
                 fication.

                 Elimination of check and lot tanks  Prevent versus cure, which is part of TQC,
                 makes it attractive to eliminate corrective provisions such as the check tanks and lot
                 tanks in plants. These tanks are installed in plant recycle systems to cope with off-
                 specification products.
                   In the past, most batch plants were unable to produce consistent batches, and
                 therefore more batches were produced and the whole was blended in a so called lot
                 tank The solution for this is to use feed forward control (in general to be double-
                 checked with separate measurements) with a feedback adjustment in the process.
                The disturbances (whether internal or external) should be incorporated in the feed
                 forward controllers to achieve TQC (see Figure 1.3 in Chapter 1). It should not be
                 underestimated that operational errors are also often a cause for off-specification
                 situations, and these must be covered by the application of automation.

                 Prevent upsets  Many provisions are installed in plants to cope with unplanned
                 situations. The release of a component to the environment is mostly covered with
                 add-on provisions such as scrubbers, incinerators, flares, emergency tanks, etc.
                 However, all of these provisions are expensive, and the best way to handle the situa-
                 tion is to modify the design into a preventive action, triggered by a question such as:

                   what provision is needed to prevent an upset?

                 A higher design pressure of a vessel in order to prevent release, or release through a
                 safety device into another process vessel, are often cheap solutions. The following is
                 a typical example (Figure 3.5). The safety provisions on an ammonia storage facility
                 asked for a very large scrubber with water, and the recovery of unlikely, but poten-
                 tially diluted, solution. Removal of the safety device was accomplished by preventing
                 upsets. In this particular situation, a potential fire was the limiting case. Elimination
   66   67   68   69   70   71   72   73   74   75   76