Page 86 - Drilling Technology in Nontechnical Language
P. 86

Chapter 3 – DRILLING A LAND EXPLORATION WELL                      77












































                 Fig. 3–22. Wellhead after cementing and adding the casing spool


                    The next blowout preventer will be nippled up on top of this spool. It
                 will be smaller than the first one and will have a higher pressure rating.

                 The side outlets that are exposed to the well have two valves attached, so
                 that if one leaks under pressure, there is a backup valve.


                    Drilling the production hole section


                    Imagine now that another hole section was drilled and another
                 intermediate casing cemented in place. Things will not be too different
                 from the intermediate section described above. This new casing is set
                 about 500 ft (150 m) above where the top of the reservoir is expected. The
                 plan now is to drill through the reservoir and about 200 ft (61 m) below it,
                 log the hole, and then run a liner.