Page 70 - Enhanced Oil Recovery in Shale and Tight Reservoirs
P. 70

Huff-n-puff gas injection in oil reservoirs                   57


                 From January to March 2010, there was a gradual oil productivity in-
              crease. The peak oil rate reached 44 bbl/d in March 2010 (a higher rate
              than what was achieved during any of the 14 months immediately prior
              to the injection test). However, the operator confirmed that the higher pro-
              duction rate might be related to workover activities on the well as opposed
              to delayed CO 2 effects. Although the Burning Tree well did not see a dra-
              matic production increase, CO 2 was able to be injected (no injectivity issue)
              (Sorensen and Hamling, 2016).
                 One reason for the poor performance in the above tests in Montana and
              North Dakota could be the too short injection duration (45 and 30 days,
              respectively). In the North Dakota test, CO 2 broke through an offset well
              about 5000 feet away in less than 2 weeks. This could be another reason
              for the poor performance. The third reason may be too low injection pres-
              sure (2000e3000 psi for both the tests).

              2.15.3 Huff-n-puff CO 2 injection in Parshall field
              EOG conducted a CO 2 injection test in NDIC 16713 in the Parshall field in
              the Mountrail County in late 2008. A horizontal well was drilled into the
              Middle Bakken and was completed using a six-stage hydraulic fracture treat-
              ment. An estimated 30 MMSCF of CO 2 were injected using a huff-and-puff
              approach. After 11 days of injection, CO 2 broke through the offset well
              NDIC 16768, located one mile west of the NDIC 16713. The oil rates
              for the test well and offset wells increased after injection.
                 The Parshall field has a high degree of natural fracturing, and the high
              mobility of CO 2 in this fractured system indicates that conformance control
              is likely a major factor in designing EOR operations. Of interest is the fact
              that three other offset wells located within one mile of the injector did not
              see CO 2 breakthrough, suggesting that understanding the local natural frac-
              ture system is key to EOR planning (Sorensen and Hamling, 2016).

              2.15.4 Eagle Ford project in La Salle County, TX
              Four wells are in huff-n-puff injection starting in 2015. Initially gas was
              injected for 6 months to fill up the reservoir void. Then wells produced
              for 2e3 months followed by 8e10 weeks. This pattern was repeated for
              four cycles. After that, a shorter cycle of 4e6 weeks of injection and soak
              time and 2 months of production was used. The average well oil rate
              and the cumulative production within the lease are shown in Fig. 2.47.
              The oil rate clearly shows the increase (about doubled) from huff-n-puff
   65   66   67   68   69   70   71   72   73   74   75