Page 38 - Estimator's Piping Man-Hour Manual 5E
P. 38

Section One~SHOP FABRICATION     21

              SPECIAL fTrUNG AND PREPARATION FOR
             INERT GAS SHIELDED ROOT PASS WELDING

                                    Butt Welds

                                NET MAN HOURS EACH
                    CARBON STEEL, CHROME ALLOY AND STAINLESS STEEL
             Pipe                                Pipe
             Size              AH                Size              All
            Inches          Thicknesses         Inches          Thicknesses
           2 "or less          0.45             26 O.D             5.37
           2-1/2               0.64             28O.D.             6.12
           3                   0.75             30O.D.             6.48
                                                          1
           4                   0.94             32O.D,             6.83
           5                   1.14             34O.D.             6.88
           6                   1.36             36O.D.             7.06
           8                   1.67             38 O.D.            7.39
           10                  1.92             40O.D.             8.23
           12                  2,06             42 O.D             9,06

           14O.D.              2,66            44 O.D.            9.87
           16O.D.              3.19            46 O.D,            10.93
           18O.D.              3.90            48 O.D             11.99
           20O.D.              4.22            54 O.D.            13.15
           24O.D.              4.68            60 O.D.            14.42

     Man hours shown will apply either with or without an internal nitrogen purge.
     For internal argon purge, increase above man hours 20 percent.
     Man hours do not include the use of an oxygen analyzer.

     Man hours do not include the installation of consumable inserts or end preparation for consumable inserts.
     For preparation of nozzle welds, 'olet welds, coupling welds, and mitre butt welds for inert gas shielded root pass
     add 100 percent to the above man hours.
     If the purge is to be held longer than the first two passes, increase the above man hours 50 percent for each
     additional pass for which the purge is held.