Page 49 - Estimator's Piping Man-Hour Manual 5E
P. 49

32   Section One-SHOP FABRICATION





                                    Labor for Welding
                                  Carbon Steel Material

                                 NET MAN HOURS EACH

            Standard   Extra
             Pipe   Heavy Pipe              SCHEDULE NUMBERS
      Size   &OD Sizes  & OD Sizes
      Ins.  3/8 "Thick  1/2" Thick  20   30   40   60   80   100   120   140   160
     2        1.4      1.8         --    1.4        1.8   --    --   _ _   2.8
     2-1/2    1.6      2.1               1.6   ._   2.1                    3.3
                              —
     3        1.7      2.4    _ _   --   1.7        2.4   --    --   --    3.9
     3-1/2    2.0      2.8               2.0   --   2.8
     4        2.3      3.3         --    2.3   --   3.3   --    4.7   ..   5.6
                              —
     5        3.0      4.2    --   ..    3.0   --   4.2         6.6   --   7.8
                                                          —
     6        3.6      5.4    --   _.    3.6   --   5.4   --    8.9   ..   10.1
     8        5.0      7.8         5.0   5.0   --   7.8   10.1   13.2   15.5   17.0
                              —
     10       6.6     10.5         6.6   6.6   10.5   12.4   15.8   22.6   --  29.5
                              —
     12       8.7     14.0    --   8.7   13.2   16.4   21.0   27.9   37.2   -.   42.7
     14 OD   11.5     19.4   11.5   11.5   18.7   23.3   30.3   38.1   52.8   _.   --
     16 OD   16.4     24.8   16.4   16.4   24.8   29.5   33.5   43.4   58.3   -
                                                                     —
     18 OD   20.1     32.6   20.1   30.3   38.1   54.3         _.    --    --
                                                    —     —
     20 OD   23.3     36.5   23.3   36.5   42.7   65.1   --  --  --  --    --
     24 OD   31.0     50.5   31.0   50.5


     Pipe Thickness: The wall thickness of the pipe determines the man hours that will apply. For
         swedged ends on double extra strong pipe thickness, use Schedule 160 man hours.
     Ends: All man hours are based on ends being furnished either plain or beveled for welding.
     Unlisted Sizes: Unlisted sizes take the next higher listing.
   44   45   46   47   48   49   50   51   52   53   54