Page 75 - Estimator's Piping Man-Hour Manual 5E
P. 75

58  Section One-SHOP FABRICATION

                     PREHEATING 90° NOZZLE WELDS


                                Carbon Steel, or Alloy Materials
                                For Temperatures Up to 400 °F

                                 NET MAN HOURS EACH
               Standard    Extra
                 Pipe    Heavy Pipe             SCHEDULE NUMBERS
     Size      & OD Sizes   & OD Sizes
      Ins.     3/8 "Thick   1/2 "Thick   20   30   40   60   80   100   120   140   160
      2          0.4        0.5     „    „   0.4   _.   0.5   ..   —   „   0.6
      2-1/2      0.5        0.6     ..   --  0.5   -   0.6   --  --   --  0,8
      3          0.5        0.8     „    ..   0.5      0.8   ..   —   ..   0,9
      3-1/2      0.6        0.8     --   --  0.6   --  0.8   -   -    --   ...

      4          0.8        0.9     --   -    0.8   --  0.9   --  1.2   ..   1.4
      5          0.9        1.2     -         0.9   --  1.2   --  1.4   „   1.6
      6          1.1        1.6     --   -    1.1   --  1.6   „   1.7   -  2.1
      8          1.4        1.8     1.4   1.4   1.4   1.7   1.8   2.3   2.6   3.0   3.5
      10         1.7        2.3     1.7   1.7   1.7   2.3   2.6   3.2   3.8   4.4   5.0
      12         2.1        2.8     2.1   2.1   2.4   3.0   3.8   4.4   5.1   5.9   7.0
      140D       2.5        3.2     2.5   2.5   3.0   3.9   5.0   5.6   6.6   7.3   8.9
      16 OD      2.9        3.9     2.9   2.9   3.9   5.0   6.1   7.2   8.3   9.1   11.6
      18 OD      3.6        4.7     3.6   4.1   5.3   6.7   8.1   8.9   10.8   11.4   14.4
      20 OD      4.7        5.5     4.2   5.5   7.0   8.6   10.0   11.6   13.2   13.5   15.5

      24 OD      5.1        6.6     5.1   7.2   8.7   10.6   12.8   14.0   16.0   16.7   18.6
     Pipe Thickness: The size of the nozzle and the wall thickness of the header or nozzle (whichever is greater)
          determines the man hours to be used. For preheating of double extra strong thickness use schedule 160
          man hours.
      Time: For reinforced 90 ° nozzle welds, add 100% to the above man hours. For 45° nozzle welds, add 50% to the above
          man hours. For reinforced 45° nozzle welds, add 150% to the above man hours. For preheating to tempera­
          tures above 400 T. but not exceeding 600 °F., add 100% to the above man hours. Preheating of coupling,
          weldolet, threadolet or socket welds should be charged at the same man hours as shown for the same size
          and schedule nozzle. Man hours for preheating are additional to man hours for welding operations.
   70   71   72   73   74   75   76   77   78   79   80