              PREHEATING BUTT WELDS AND ANY TYPE
                             OP FLANGE WELDS
                                     Labor Only

                               Carbon Steel, or Alloy Materials
                               For Temperatures Up To 400 °F.

                                NET MAN HOURS EACH
                                                                      - ­
                 Standard   Extra
                   Pipe   Heavy Pipe           SCHEDULE NUMBERS
         Size    & OD Sizes  & OD Sizes
         Ins.    3/8" Thick   1/2 "Thick   20   30   40   60   80   100   120   140   160
         2         0,2      0.3     ..   ..   0.2   ..   0.3   „   „      0.4
         2-1/2     0.3      0.4     --   --  0.3   --  0.4   --  --       0.5

         3         0.4      0.5          „   0.4   ,.   0,5      ..       0.6
         3-1/2     0.4      0.5     ...   --  0.4   --  0.5      -        0.8
         4         0.5      0.6     --   ..   0.5   --  0.6   ..   0.8    0.8
         5         0.6      0.8     --   -   0.6   -   0.8   ..   0.8   -  0.9
         6         0.7      0.9     ..       0.7   ..   0.9   --  1.1   --  1.3
         8         0.8       1.1   0.8   0.8   0.8   1.1   1.1   1.5   1.6   2.0   2.1
         10         1.1      1.5   1.1   1.1   1.1   1.5   1.7   2.0   2.3   2.8   3.2
         12         1.3      1.7   1.3   1.3   1.6   1.9   2.4   2.8   3.2   3.7   4.5
         1400       1.6      2.1   1.6   1.6   1.9   2.5   3.0   3.7   4.2   4.9   5.6

         16 OD      1.9      2.8   1.9   1.9   2.5   3.2   3.8   4.6   5.1   6.2   7.2
         18 OD     2.2      3.0    2.2   2.6   3.5   4.2   5.1   5.9   6.7   7.2   8.9
         20 OD      2.6      3.5   2.6   3.5   4.4   5.3   6.3   7.4   8.3   9.4   10,9
         24 OD     3.1      4.2    3.1   4.5   5.4   6.6   7.9   8.8   9.9   11.3   12.9

     Pipe Thickness: The wall thickness of the material determines the man hours that will apply. For preheating of
          double extra strong material, use Schedule 160 man hours.
     Mitre Welds: For preheating of mitre welds, add 50% to above man hours.
     Man Hours: Man hours for preheating are additional to charges for welding operations.
     Preheating: For preheating to temperatures above 400°F. but not exceeding 600°F., add 100% to the above man
          hours.