Page 70 - Estimator's Piping Man-Hour Manual 5E
P. 70

Section One-SHOP FABRICATION     53

                   BORING INSIDE DIAMETER OF PIPE
              AND INSTALLING STRAIGHTENING VANES


                                NET MAN HOURS EACH
           Nominal           Boring I.D.           Installing Straightening
           Pipe Size          of Pipe                    Vanes
            Inches          Carbon Steel      Carbon Steel        Alloy
             4                  8.3               6.4               9.6
             5                  99                7.4              11.1
             6                 11.3               9.1              12.9
             8                 14.8              10.7              16.0
             10                17.7              11.8              17.7
             12                21.7              13.2              20.1
             14                25.0              14.9              22,3

             16                30.0              16.5              25.0
             18                37.3              18.7              28.0
             20                48.9              21.0              31.5
             24                67.0              25.6              38.5
             26                 ..               30.4              45.8
             28                 --               33.6              50.7
             30                 --               38.9              58.3

             32                 ..               45.0              67.7
             34                 --               50.7              76.2
             36                 --               58.3              87.5
             38                 --               65.2              98.1
             40                 --               72.2             108.2
             42                 --               79.4             119.2

     Man hours for boring I.D. only include boring pipe for a length of four times nominal pipe size.
     Man hours for installing straightening vanes are based on installing vanes in pipe where boring the I.D. of pipe is
     not required. If boring I.D. of pipe is required or specified, add boring man hours as shown above.