Page 68 - Estimator's Piping Man-Hour Manual 5E
P. 68

Section One-SHOP FABRICATION 51

                       MACHINING INSIDE OF PIPE

                                     Built-Up-Ends
                                  Carbon Materials Only


                                                        Built Up Ends on Inside
                                                       Diameter of Pipe and Fittings
                                                      with Weld Metal to Provide for
                  Machining Inside of Pipe             Specified Outside Diameter
                  Net Man Hours per End                 of Machined Backing Ring
                      Standard      Double
                     Extra Strong   Extra Strong                    Net
           Size      & Sch. Nos. to   & Sch. Nos.      Size       Man Hours
          Inches     100 Inclusive   120, 140 & 160   Inches       per End
          2 or less     0.4          0.6              2 or less     0.5
          2-1/2         0,4          0.6              2-1/2          0.5

          3             0.4          0.6              3              0.6
          3-1/2         0.4          0.7              3-1/2          0.6
          4             0.6          0,7              4              0.7
          5             0.7          0.8              5              0.8
          6             0.7          0.9              6              0.9
          8             0.9           1.1             8              1.2
          10            1.0           1.3             10             1.7
          12            1.1           1.5             12             2.1
          HOD           1.3           1.8             14             2.6

          16 OD         1.5           2.1             16             3.2
          18 OD         1.8           2.4             18             3.9
          20 OD         2.1           2.9             20             4.7
          24 OD         2.9           3.8             24             7.1

     Machining: Man hours for machining the inside of straight pipe are for any taper bore from 10° through 30°
          included angle. For machining the ends of bends add 100% to the above man hours. For counterboring (up
          to a maximum of 2" in length), add 50% to the above man hours. For machining to a controlled "C"
          dimension (as required for power piping critical systems), add 225% to the above man hours.
     Cutting and Beveling: Man hours do not include cutting and beveling. See respective tables for these charges.

     Built-UpEnds: Man hours for built-up ends are for building up the I.D. of straight pipe, bends or fittings, at the
          ends with weld metal and grinding where it is necessary for proper fit of backing rings.