Section Otie-SHOP FABRICATION    67

        MAGNETIC OR DYE PENETKANT INSPECTION
                          OF WELDED JOINTS

                             All Thicknesses and Schedules

                                 NET MAN HOURS EACH
                          MAGNETIC                        DYE PENETRANT
       Size
      Inches      Butt Welds     Nozzle Welds        Butt Welds    Nozzle Welds
     2 or less       0.6            0.9                 0.8             1.3
     2-1/2           0.7             1.1                0.9             1.4
     3               0.8             1.2                1.1             1.6
     3-1/2           0.9             1.4                1.2             1,9
     4               1.1             1.6                1.5             2. 2

     5               1.4             2.1                1.9             2.8
     6               1.7             2.6                2.3             3.5
     8               2.0             3.0                2.8             4.1
     10              2.5             3.7                3.3             5.0
     12              3.1             4.7                4.2             6.3
     14 OD           3.4             5.2                4.6             6.9
     16 OD           3.9             5.8                5.2             7.9

     18 OD           4.4             6.6                5.8             8.7
     20 OD           4.8             7.2                6.5             9.7
     24 OD           5.6             8.5                7.5             11.1
     Man hours above are for a single inspection. When specifications call for multiple inspections during the progress
     of welding, the man hours shown above will apply for each of the total number of inspections.
     Magnetic particle or liquid penetrant inspection of weld end preparations should be charged at the same man
     hours as comparable inspection of the same size butt weld.
     For inspection of reinforced nozzle welds, add 150% to the above man hours to include both the nozzle weld and the
     pad weld.
     For inspection of slip-on flange welds add 50% to the above man hours.
     For inspection of small connections such as couplings, bosses, thredolets and weldolets use the man hours shown