88   Section Two-FIELD FABRICATION

                  ATTACHING       FLANGES—SLIP-ON TYPE


                     Man Hours Slipping on Flange, Manual Welding at Front and Back
                     Carbon Steel Material, Straight Pipe, Bends, Headers and Nozzles

                                 NET MAN HOURS EACH
           Pipe                       SERVICE PRESSURE RATING
           Size
          Inches     150 LB.  300 LB.  400 LB.  600 LB.  900 LB.  1500 LB.  2500 LB.
           1           0.9     1.0      1.4     1.4      1.6     1.8     2.1
           1-1/4       1.0     1.2      1.4     1.4      1.8     2.1     2.3
           1-1/2       1.0     1.3      1.4     1.4     1.8      2.1     2.3

           2           1.3     1.4      1.8     1.8     2.4      2.7     3.0
           2-1/2       1.5     1.7      2.3     2.3     3.0      3.3     3.6
           3           1.8     2.1      2.9     2.9     3.6      4.0     4,4
           3-1/2       2.2     2.4      3.3     3.3     --               -
           4           2.4     2.6      3.5     3.8     4.8      5.4     5.9
           5           3.0     3.3     4.5      4.8     6.1      6.7     7.4
           6           3.6     3.9     5.2      5.9     7,2      8.1     8.9
           8           5.1     5.4     7.3      8.0     9.9     11.0    12.0
           10          6.3     6.8     9.0     11.1     12.5    14.0    15.5
           12          7.7     8.3     11.0    13.7     15.3    17.2    19.0
           140.D.      9.0    10.0     13.0    16.2     17.7    19.8
           16 O.D.    10.5    11.3     15.0    18.4    20.1     22.4     ..
           18O.D.     12.2    13.5     17.5    21.1    23.7     26.6
           20 O.D.    14.6    16.0     21.1    23.7    27.5     30.8
           24 O.D,    18.3    20.1     25.6    31.2    34.8     38.9     .,
           26 O.D.             _       27.7    33.7     37.8     _       _
           30 O.D.     _       __      32.0    38.9     43.5     .._     _
           34 O.D.     _               36.2    44.1     49.3     _       _
           36 O.D.     ._      _       38.4    46.7     52.2     _
                                                        _
           42 O.D.     -       -       44.7    54.5              —       —

      Flanges: Man hours are for field labor only. The price of welding materials and the  flange must be added in all
            cases.
      Pipe Thickness: Man hours are for any wall thickness of pipe used with listed  flanges.
      Preheating: If specified or required by codes, add for this operation. See man hours for pre-heating.
      Stress Relieving: If specified or required by codes, add for this operation. See man hours for stress relieving.