Page 110 - Estimators Piping Man Hour Manual
P. 110

Section Two-FIELD FABRICATION     93



                                 Man Hours—Welding Only
                                  Carbon Steel Material
                                 NET MAN HOURS EACH
            Standard  Extra
             Pipe   Heavy Pipe              SCHEDULE NUMBERS
      Size  & OD Sizes &  OD Sizes
      Ins.  3/8 "Thick 1/2"  Thick  20  30  40  60  80    100   120  140  1  160
                              __    __         __         __
     1        0.7      0.8          __   0.7        0.8         .-         1.0
     1-1/4    0.8      0.8    ..         0.8   --   0.8   -- __  -- __  --  1,1
     1-1/2    0.8      0.9    --    --   0.8   --   0.9                    1.3
                                    __         __         __    __
     2        1.0      1.0               1.0   __    1.0  __               1.6
     2-1/2    1.2      1.3    —     _-   1.2         1.3        --         L8
                              --
                              __    __         __         __    __
     3        1.3      1.4               1.3         1.4                   2, 1
     3-1/2    1.4      1.6    --    --   1.4   --    1.6        --
                                                          —
     4        1.5      1.8    --    --   1.5   ..    1.8  --    2.8        3.0
     5        1.7      2.1    --    --   1.7   -.    2.1  --    2.9  --    3.8
                                                                     __
     6        2.0      2.5    --         2.0   _-   2.5   _.    3.8        4.9
                                    —
     8        2.6      3.3    2.6   2.6  2.6   3.0   3.3  4.6   6.0   7.5  8.6
     10       3.1      4.0    3.1   3.1  3.1   4.0   5.1  I  6.8  9.4  11.4  13.1
     12       3.6      4.7    3.6   3.6  4.1   5.2  6.6  1  9.9  12.2  15.3  17.9
     HOD      4.3      5.7    4.3   4.3  5.0   6.8  9.6  13.2  16.2  19.2  22.7
     16  OD   5.0      6.6    5.0   5.0  6.6   8.4  12.4  19.5  20.7  25.0  27.7
     18 OD    5.9      7.7    5.9   6.8  8.6  11.2  16.4  21.8  25.6  29.9  33.7
     20 OD    6.3      8.4    6.3   8.4  9.4  13.8  19.5  26.0  31.9  37.0  40.8
     24 OD    6.9     10.1    6.9   --  13.3  20.1  25.2  35.8  43.5  49.3  59.3

     Pipe  Thickness:  Wail  thickness  of  the  pipe  determines  the man hours that will apply, for  butt
         welds of double extra strong materials, use schedule 160 man hours.
     Mitre  Welds;  Add 50% to butt  weld  man hours.
     Cutting and Beveling Pipe: Man hours do not include cutting and beveling of pipe. See respective tables for these
          charges.
     Preheating: If specified or required by codes, add for this operation. See man hours for preheating.
     Stress Relieving: Stress relieving  of welds in carbon steel materials  is required  by the  A.S.A. code for pressure
          piping, where the wall thickness is 3/4" or greater.
          All sizes of butt welds shown below the ruled lines are 3/4" or greater in wall thickness and must be stress
          relieved.
          Where stress relieving is required an extra charge should be made. See man hours for stress relieving.
     For  Geneml  Notes  on welding,  see page 92.