Section Two-FIELD FABRICATION     97

                  90° WELDED NOZZLES—REINFORCED
                       Labor for Cutting and Welding Carbon Steel Material

                                 NET MAN HOURS EACH
                Standard   Extra
                 Pipe    Heavy Pipe             SCHEDULE NUMBERS
        Size   & OD Sizes  & OD Sizes
        Ins.    3/8" Thick  1/2 "Thick  20  30  40  60  80  100  120  140  160
        1-1/2     5.0        5.4    -    --   5.0  --  5.4  --             7.7
        2         5.3        5.9    ...  —    5.3  ..  5.9  —    ..   ..   9.9
        2-1/2     5.8        7.0    -    -    5.8  --  7.0  --   -    -   10.8

        3         6.7        7.9    ..   .,   6,7  —   7.9  —    ..   „   12.0
        3-1/2     7.5        8.7    -    --   7.5  --  8.7  --   --        --
        4         8.1       10.0    --   -    8.1  -   10.0  -  12.5      15.3
        5         9.8       11.8    -    -    9.8  -   11.8  -  15.1      18.4
        6         10.2      12.8             10.2      12.8     18.5      23.1
        8         11.7      14.5   11.7  11.7  11.7  13.4  14.5  19.8  24.5  [29.3  32.8
        10        12.7      16.3   12.7  12.7  12.7  16.3  20.2  26.0  31.0  34.8  39.1
        12        14.2      18.3   14.2  14.2  15.3  20.3  26.3  1 35.5  39.5  44.6  47.7
        14 OD     16.0      20.7   16.0  16.0  17.8  24.3  34.5  44.0  46.8  52.6  60,6

        16 OD     17.9      23.2   17.9  17.9  22.8  30.1  40.1  54.8  57.5  60.6  70.0
        18 OD     19.1      23.8   19.1  22.1  30.0  37.4  45.0  59.5  61.9  65,3  87.6
                                                 ••••••Mil
        20 OD     21.1      26.6   21.1  26.4  32.3  47.2  55.5  63.8  73.8  84.6  98.4
        24 OD     22.3      27.7   22.3  30.3  36.5  52.5  59.5  72.4  85.7  99.0  115.0
                                                     ,  n
          All Nozzles other than 90° should be charged at the man hours shown for 45" nozzles.
     Pipe  Thickness:  Wall thickness of the  pipe used for the  nozzle determines the  man  hours that will apply. For
          nozzles of double extra strong pipe thickness  use schedule 160 man hours.
     Reinforcement:  Man hours given above include the labor requirements for reinforcement produced by building up
          the nozzle weld, or by the use of reinforcing rings or saddles as may be specified.
     Preheating: If specified  or required by code, add for this operation. See man hours for preheating. The size and wall
          thickness of header (not the size of the nozzle) determines the preheating  man hours.
     Stress Relieving: Stress relieving of welds in carbon  steel material is required  by the  A.S.A. code for pressure
          piping, where the wall thickness is 3/4" or greater. The size and wall thickness of the header determines the
          man hours to be used for stress relieving. All pipe sizes shown below the ruled line are 3/4" or greater in
          wall thickness and must be stress relieved.  Where stress relieving is required  an extra charge should be
          made. See man hours for stress relieving.
     For  General  Notes  on welding, see page 92.