Page 116 - Estimators Piping Man Hour Manual
P. 116

Section Two-FIELD FABRICATION     99

                           45° WELDED NOZZLES


                               Labor for Cutting and Welding
                                  Carbon Steel Material

                                 NET MAN HOURS EACH
            Standard  Extra
             Pipe   Heavy Pipe               SCHEDULE  NUMBERS
      Size  6 OD Sizes ft  OD Sizes
      Ins.  3/8 "Thick 1/2"  Thick 20  30  40  60   80    100  120   140   160
     1        2.8      2.9          ""**  2.8       2.9         --         4.1
     1-1/4    2.9      3.2    ——         2.9        3.2                    4.7
     1-1/2    3.2      3.6               3.2   «,«.  3.6  * ~        ~     5.4
     2        3.3      4.1               3.3        4.1         ._         7.1
     2-1/2    3.8      5.1    _-         3.8   —    5.1              —     7,9
                                    —                     —
     3        4.4      5.9               4.4        5.9                    8.9
     3-1/2    4.9      6.4    —    --    4.9        6.4   —     —    —
                                               —                     __
                                               __
     4        5.5      7.6    ..         5.5        7.6   --    9.4       11.4
                                   —
     5        6.7      9.1               6.7        9.1   --   11.7  ..   14.4
                              —    —           —
     8        7.1     10.0               7.1        10.0       14.5  ..   18.4
     8        8.6     11.7    8.6  8.6   8.6  11.1  11.7  15.9  20.11 25.1  28.6
     10       9.6     13.7    9.6  9.6   9.6  13.7  16.6  21.8  28.1  !  36.2  43.7
     12      10.9     15.7   10.9  10.9  13.0  17.5  22.9  124.2  38.6  45.7  52.2
     14 OO   12.4     18.2   12.4  12.4  15.3  21.4  30.1  38.4  45.9  51.6  64.2
     16 OD   14.2     20.2   14.2  14.2  20.2  26.8  35.3  48.7  54.8  61.2  74.1
     18 OD   15.5     21.6   15.5  20.1  25.5  j  34.3  40.6  59.1  65.7  71.0  92.7
     20 OD   17.1     23.7   17.1  22.7  29.8  I 43.3  46.9  68.3  74.9  81.5  104.1
     24  OD  18.8     26.6   18.8  31.8  35.5  1 48.0 ________ 86.8  93.4  104.3  121.8
                                                    55.0

     Pipe  Thickness:  Wall  thickness  of  the  pipe used for  the nozzle determines  the man hours that
        will apply.  For nozzles of double extra  strong pipe thickness, use  schedule  160 man hours.
     Reinforcement:  Man hours  given  above are  for  plain  nozzles  only.  For  use of gusset plates,
        etc., as  stiffeners,  not for  reinforcement,  add  25% to the  net  man  hours  shown above.  If
        reinforcement  is  required  and produced  by  building up  the  nozzle weld, or  by the  use of
        reinforcing rings or  saddles as  specified  use man hours for 45° reinforced  nozzles.
     Preheating:  If  specified  or  required  by codes, add for  this operation.  See man hours for  pre-
        heating.  The  size  and  wall  thickness  of the header  (not the size of the nozzle)  determines
        the preheating  man hours.
     Stress  Relieving:  Stress  relieving  of welds in carbon steel material is  required by the A.S. A.
        code  for pressure  piping, where  the  wall thickness is 3/4"  or greater.  The size and wall
        thickness of the header  determines the man hours to be used for stress relieving.  All pipe
        sizes  shown  below  the ruled  line are  3/4"  or greater in wall thickness and must be stress
        relieved.  Where stress  relieving  is  required  an  extra  charge  should be made.  See man
        hours for stress relieving.
     General  Notes: For additional notes on welding see page 92.