104   Section Two-FIELD FABRICATION

                    END CLOSURES—PRESSURE TYPE


                                   Carbon Steel Material

                                 NET MAN HOURS EACH
                                               SCHEDULE  NUMBERS
      Nom.  Standard    Extra
      Pipe    Pipe    Heavy Pipe                                         XX Hy.
      Size  & OD Sizes  & OD Sizes                                         or
       Ins.  3/8" Thick  1/2"  Thick  40  60    80    100   120     140   160
      1-1/2    0.9       1.0      0.9           0.9   ..                   2.3
                                         —                   —      —
                                         __
      2        1.2       1.3      1.2           1.3          --            3.S
      2-1/2    1.3       1.5      1.3           1.5                 —      4.3
                                                      —
      3        1.5       1.8      1.5    --     1.8   __     --            4.5
      3-1/2    1.8       2.1      1.6           2.1
      4        1.8       2.4      1.8    _.     2.4   --     5.6           8.0
                                                                    —
      5        2.3       2.9      2.3    ..     2.9   ..     7.5    ..     7,9
      6        2.8       3.3      2.6           3.3          9.3          10.2
                                                                    —
      8        3.7       4.7      3.7           4.7   8.9   12.5   14.8   15.6
      10       4.6       5.9      4.6    5.9   10.3   12.7  21.4    23.0  24.7
      12       5.5       7.2      6.7    7.7   13.0   18.9  28.6    31.2  33.7

      14       6.6       8.6      8.0    9.9   15.1   20.9   32.9   44.5  46.3
      18       7.4       9.7      9.7   12.5   16.8   23.5   37.9   56.1  58.8
      18       9.0      11.3     13.9   16.2   21.8   29.6   42.8   67.6  71.3
      20       9,7      12.5     16.8    19.8   27.0  35.8   47.8   79.1
      24      10.6      14.9     19.6    23.5   32.2  42.1   52.2   --
                                                                           —
      Pipe  Thickness:  Wall  thickness  of  pipe  determines  the man hours that will apply.  For double
         strong pipe thickness  use schedule  160 man hours.
      Construction:  End closures  such as  orange peel, saddle, or  flat plate type.
      Preheating;  If  specified  or  required  by codes,  add for  this  operation.  See man hours  for  pre-
         heating.
      Stress  Relieving:  Stress  relieving  of welds in carbon steel material  is  required by the  A. S. A.
         Code for pressure piping where the wall thickness is  3/4"  or greater.
         All  sizes  of  butt  welds  shown  below  the ruled  lines are  3/4"  or  greater  in wall  thickness
         and  must  be  stress  relieved,  if  the  end  closure  involves  a circumferential  weld.  Where
         stress relieving  is  required,  an  extra  charge  should  be  made.  See man hours for stress
         relieving.
      Unlisted  Sizes:  Unlisted sizes take the next higher  listing.