1O6   Section Two-FIELD  FABRICATION

         LARGE      O.D. PIPE END CLOSURES—PRESSURE
                                      TYPE


                                  Carbon  Steel Material
                                 NET  MAN HOURS EACH
      O.D.                           WALL THICKNESS  IN.
      Pipe
      In.     .875     .500    .750     1.00     1.25    1.50     1.75    2,00
      26      33.8     40.7     53.2    65.0     76.0     86.6    96.2    105.6
      28      35.2     43.0     57.0    69.7     81.5     92.6    102.8   113.4
      30      36.9     45.2     60.1    73.5     85.9     97.6    108.2   119.3
      82      38.5     47.1     62.5    76.5     89.4    101.6    112.7   124.3
      84      40.0     49.0     65.0    79.5     93.0    105.6    117.2   129.2
      36      41.4     50.6     67.3    82.2     96.2    109.3    121.2   133.7
      38      42.8     52.4     69.6    85.2    100.0    113.2    125.6   138.5
      40      44.6     54.5     72.5    88.6    103.6    117.6    130.5   144.0
      42      46.4     56.8     75.4    92.2    107.7    122.4    135.7   149.6
      44      47.9     58.6     77.9    95.2    111.3    126.4    140.2   154.6
      46      87.4     60.7     80.6    98,5    115.2    130.9    145.1   160.1
      48      51.2     62.7     83.2    101.7   118.9    135.1    149.9   165.3
      54      54.8     66.9     88.9    108.7   127.1    144.3    160.0   176.5
      60      58.5     71.6     95.1    116.3   136.1    154.6    171.5   189.2
              2.25     2.50    2.75     3.00     3.25    3.50     3.75    4.00
      26      114.7   124.8    133.5    142.0   151.9    159.2    166.9   174.9
      28      123.2   134.0    143.3    152.5   163.1    170.9    179.1   187.7
      30      129.6   141.0    150.7    160.4   171.6    179.8    188.4   197.5
      32      135.0   146.9    157.1    167.1   178.8    187.4    196.4   205.8
      34      140.3   152.7    163.2    173.7   185.9    194.8   204.1    213.9
      36      145.1   157.9    168.7    179.6   192.2    200.7   210.4    220.5
              4.25     4.50    4.75     5.00     5.25    5.50     5.75    6.00
      26      182.1   189.5    197.3    204.0   211.0    218.2   225.6    232.0
      28      195,4   203.4    211.8    219.0   226.4    234.1   242.0    248.7
      80      205.7   214.1    222.8    230.3   238.1    246.3   254.6    261.7
      32      214.8   223.0    232.1    240.0   248.2    256.7   265.4    272.8
      34      222.7   231.8    241.3    249.6   258.1    266.8   275.9    283.6
      36      229.6   239.1    248.9    257.4   266.1    275.2   284.5    292.5

      Construction:  End  closures  as such are  field  fabricated closures; orange  peel,  saddle, or flat plate type.

      Preheating: If specified or required by  codes, acid  for this  operation. See  man hours for  preheating.
      Stress Relieving: Stress relieving of welds in carbon steel material is required by the A.S.A. Code of Pressure Piping
       where the  wall thickness is  ;V4" or greater.
       Above wall thickness  .750 through  6.00 must  be stress relieved,  if the  end closure involves a circumferential weld.
       See respective  table for stress relieving.