Page 131 - Estimators Piping Man Hour Manual
P. 131

114   Section Two-FIELD FABRICATION

                   THREADING       PIPE—INCLUDING CUT


                                Labor For Cut and Thread Only
                                  Carbon Steel Material

                                 NET MAN HOURS EACH
                 Standard  Extra Hvy.
         Pipe     Pipe&     Pipe&               SCHEDULE NUMBERS
         Size    O.D. Sizes  O.D. Sizes
        Inches   3/8" Thick  1/2" Thick  20  30  40  60  80  100  120  140  160
      2 "or Less   0.20     0.30             0.20      0.30               0.42
      2-1/2"       0.27     0.40    —    ~   0.27  --  0.40  --  --   ..  0.47

      3            0.30     0.42             0.30      0.42               0 58
      4            0.42     0.58             0.42      0.58     0.84      0.90
      5            0.54     0.78    --   --  0.54      0.78  -  0.91  --  1.07
      6            0.70     0.93    --   --  0.70  --  0.93     1.18  „   1.35
      8            0.97     1.35   0.97  0.97  0.97  1.26  1.35  1.64  1.83  2.04  2.38
      10           1.38     1.84    1.38  1.38  1.38  1.84  2.11  2.44  2.58  3.08  3.65
      12           1.53     2.44    1.53  1.53  2.07  2.75  2.90  3.17  3.65  4.14  4.38

      140.D.       2.07     2.67    2.07  2.07  2.67  2.95  3.39  3.85  4.14  -
      16 O,D.      2,37     3.45    2.37  2.37  3.45  3.71  4.14  4.38  4.87  -•
      18O.D.       2.95     4.14    2.95  3.65  4.14  4.38  4.87  5.42  --
      20O.D.       3.54     4.72    3.54  4.72  5.68  6.16  6.49  --  --
      24 0,D.      5.18     6.89    5.18  7.23  7.67  7.93  8.37  --  --  -  ..
      Above man hours are for die cut IPS pipe threads only.
      For threading the ends of bends, add 100% to the above man hours.