Page 130 - Estimators Piping Man Hour Manual
P. 130

Section Two-FIELD  FABRICATION    113

         FLAME BEVELING LABGE O.D. PIPE FOR WELDING


                               Labor For Straight Pipe Only
                                  Carbon Steel Material

                                NET MAN HOURS EACH
           0. D. Pipe                  WALL THICKNESS IN INCHES
            Size
            Inches             .375             .500              .750
             26                3.27              4,31              4.87
             28                3.75              4.68              5.24

             30                4.00              5.05              5.69
             32                4.43              5.39              5.95
             34                4.84              5.95              6.43
             36                5.39              6.47              6.91
             38                6.10              7.17              7.47
             40                6.80              7.85              8.18
             42                7.59              8.66              8.96
             44                8.59              9.48              9.89
             46                9.63             10.41             10.89
             48               10.89             11.45             11.82

             54               12.25             12.87             13.31
             60               13.62             14.31             14.79
     For Mitre Bevels add 50% to the above man hours.
     Above man hours are for flame "V" beveling only and do not include cutting or internal machining. See respective
     man hour tables for these charges.
     For beveling on the ends of bends or shop trimmed fittings, add 50% to the above man hours.