112   Section Two-FIELD FABRICATION

                  FLAME BEVELING PIPE FOR WELDING


                                   "V" Type Bevels

                                 Labor for Straight Pipe Only
                                   Carbon Steel Material

                                 NET MAN HOURS EACH
        Pipe  Standard Extra Hvy.
        Size  Pipe&  Pipe&                 SCHEDULE NUMBERS
       Inches O.D. Sizes O.D. Sizes
            3/8" Thick 1/2 "Thick  20  30  40  60   80   100   120   140  160

      2 "or less  0.08  0.12  ..    „   0.08   „   0.12   „     ..   „    0.16
      2-1/2"   0.09   0.14    --    --  0.09   -   0.14   -     --   --   0,18
                              _
      3        0.12   0.16          --  0.12   --  0.16   -     -         0-22
      4        0.16   0.22    --    ..  0.16   --  0.22   -    0.30  -    0.32
      5        0.20   0.28          ..  0.20   --  0.28   „    0.35  ...  0.39
      6        0.26   0.35    -     --  0.26   --  0.35   --   0.45  -    0.49
      8        0.37   0.51   0.37  0.37  0.37  0.46  0.51  0.60  0.68  0.75  ._
      10       0.51   0.72   0.51  0.51  0.51  0.72  0.78  0.86  0.95
      12       0.55   0.86   0.55  0.55  0.68  1.02  1.08  1.18  -         -

      14O.D.   0.57   1.02   0.77  0.77  0.91  1.13  1.31  --   -          -
      16O.D.   0.86   1.27   0.86  0.86  1.27  1.40  1.55  ..
      18 O.D.  1.11   1.58   1.11  1.30  1.58  1.77  ..   --    --   --    -
      20O.D.   1.35   1.77   1.35  1.82  1.95  2.15       --    --   -     -
      240.D.   2.04   2.60   2.04  2.74  2.88  -    --    --    --
      For mitre bevels add 50% to the above man hours.
      Above man hours are for flame "V" beveling only and do not include cutting or internal machining. See respective
      man hour tables for these charges.
      For beveling on the ends of bends or shop trimmed fittings, add 50% to the above man hours.