Page 137 - Estimators Piping Man Hour Manual
P. 137

120   Section Two-FIELD FABRICATION

                       INSTALLING FLOW NOZZLES

                                 Holding Ring Type


                               Carbon Steel and Alloy Materials

                                 NET MAN HOURS EACH
                        FLOW NOZZLES                        FLOW NOZZLES
          Pipe                                Pipe
          Size       Carbon                   O.D.       Carbon
         Inches       Steel       Alloy      Inches       Steel       Alloy
         4            37.8        44.2         26         165.6       198.7
         5            41.1        47.3         28         189.6       222.0

         6            45.8        53.0         30         217.4       249.9
         8            55.2        62.5         32         248.5       282.3
         10           63.0        72.7         34         283.7       316.2
         12           71.0        82.6         36         319.1       357.4
         14O.D.       77.6        91.2         38         357.5       404,0
         16O.D.       87.6        103.4        40         400.5       456.5
         18O.D.       98.8        117.2        42         448.5       516.0
         20O.D.       111.0       133.7                    --          ..
         240.D.       140.3       170.7        --          --          -
      Man hours include internal machining and nozzle installation.

      For installing welding type flow nozzles,  add for the bevels, butt weld, butt weld preheat, and any other labor
      operation or non-destructive testing operation required for the butt weld. See respective tables for these charges.
   132   133   134   135   136   137   138   139   140   141   142