124   Section Two-FIELD FABRICATION

                    PREHEATING 90° NOZZLE WELDS


                               Carbon Steel, or Alloy Materials
                               For Temperatures Up To 400"F

                                 NET MAN HOURS EACH
            Standard  Extra
             Pipe   Heavy Pipe               SCHEDULE  NUMBERS
      Size  & OD Sizes & OD Sizes
      Ins.  3/8" Thick 1/2"  Thick  20  30  40  60   80   100   120  140   160
      2       0.5      0.6    --         0.5   --    0.6        --         0.7
      2-1/2   0.6      0.7          ..   0.6         0.7  --          —    0.9
      3       0.6      0.9    --         0.6   --    0.9                   1.0
      3-1/2   0.7      0.9          --   0.7         0.9  --    —     ._
                                    __
      4       0.9      1.0    _.         0.9   ..    1.0  --    1.4   --   1.7
      5       1.0      1.4          --   1.0   --    1.4  --    1.7   ..   1.8
                              —
      6       1.3      1.8    --    --   1.3   --    1.8        2.0        2.4
                                                          —           —
      8       1.8      2.1    1.7   1.7  1.7   2.0   2.1  2.7   3.1   3.5  4.1
      10      2.0      2.7    2.0   2.0  2.0   2.7   3.1  3.8   4.5   --   5.9

      12      2,5      3.3    2.5   2.5  2.8   3.5   4.5  5.2   6.0   _.   8.3
      14 OD   3.0      3.8    3.0   3.0  3.5   4.6   5.9  6.6   7.8       10.5
                                                                      —
      16  OD  3.4      4.6    3.4   3.4  4.6   5.9   7.2  8.5   9.8   ._  13.7
      18  OD  4.2      5.5    4.2   4.8  6.3   7.9   9.6  10.5  12.7  ._  17.0
      20 OD   5.0      6.5    5.0   6.5  8.3  10.1  11.8  13.7  15.6  ._   --
      24 OD   6.0      7.8    6.0   8.5  10.3  12.5  15.1  16.5  18.9  --
                                                                           —
      Pipe Thickness: The size  of the  nozzle and  the  wall  thickness of the  header or  nozzle  (whichever  is greater)
           determines  the  man hours to be used. For preheating  of double extra  strong thickness use schedule 160
          man hours.
      Time: For reinforced 90° nozzle welds, add  100% to the above man hours.
           For 45° nozzle welds, add 50% to the above man hours.
           For reinforced 45"nozzle welds, add  150% to the above man hours.
           For preheating to temperatures above 400°F. but not exceeding 600°F., add 100% to the above man hours.
           Preheating of coupling,  weldolet,  threadolet  or socket welds should be charged at the same man hours as
          shown for the same size and schedule nozzle,
           Man hours for preheating are additional to man hours for welding operations.