Page 146 - Estimators Piping Man Hour Manual
P. 146

Section Two-FIELD FABRICATION     129

                       RADIOGRAPHIC INSPECTION

                             Field X-Ray Of Butt Welds


                                  Carbon Steel Material

                                NET MAN HOURS EACH
                                           Wall Thickness     Wall Thickness
         Nominal                            Greater Than       Greater Than
           Pipe         Wall Thickness      Extra Strong     Schedule 120 Thru
           Size        Thru Extra Strong  Thru Schedule 120  Double Extra Strong
         2 Or Less          0.86                --                1.13
         3                  0.86                --                1.13

         4                  0.98               1.13               1.27
         5                  1.07               1.23               1.40
         6                  1.20               1.40               1.56
         8                  1.35               1.54               1.75
         10                 1.51               1.73               1.97
         12                 1.71               1,97               2.23
         14                 1.86               2.14               2.42
         16                 2.08               2.39               2.70
         18                 2.32               2.67               3.01
         20                2.55                2.94               3.34

         24                3.15                3.62               4.08
     Man hours listed above cover radiographic inspection of butt welded joints by x-raying.
     For radiographic inspection of mitre butt welds, add 50% to above man hours.
     For radiographic inspection of slip-on flange welds, add 100% to above man hours.
     For radiographic inspection of nozzle welds add 200% to above man hours.