Section One


                              SHOP

                             FABRICATION

                              OF


                             PIPE
                             AND


                              FITTINOS




                              It  is  the Intent and express purpose  of  this sec-
                              tion to cover  as nearly as possible all operations
                              which  may be  encountered  in a  shop  engaged  in
                              the pref abrication  of process piping  for  any type
                              of  industrial or  chemical plant.
                              The  man hours listed  for  the various  operations
                              are  for  labor  only,  and  have no bearing  on ma-
                              terials  which  must  be  added  in all  cases  for a
                              complete  labor  and material  estimate.
                              All  labor  for  unloading  from  railroad  cars on
                              trucks, storing in fabrication yard  or warehouse,
                              hauling  to fabrication  area,  fabricating  and re-
                              turning  to storage area  or  loading  for  delivery
                              to erection  site  have been  given due considera-
                              tion  in the  man hours  listed.  No consideration
                              has  been given  to overhead or profit  in any way.

                              For  alloy  and non-ferrous  fabrication, apply the
                             percentages  which  appear  under  Section  Three
                              to  the  following  pages  listing  the  various  shop
                              fabrication  operations.