Page 19 - Estimators Piping Man Hour Manual
P. 19

2  Section One-SHOP FABRICATION

                SHOP HANDLING PIPE FOR FABRICATION
                                   Carbon Steel  Material
                              Wall Thickness Through Schedule 160

                               DIRECT MAN HOURS PER FOOT

       Pipe Size            Schedule            Schedule             Schedule
        Inches               10 to  60          80 to  100          120  to  160

        1/4           . . .  0 029                0.031               0.033
        3/8                  0. 029  .            0.031               0.035
        1/2                  0. 030               0.033               0.036
        3/4           . . .  0. 030               0.034  . . . . . . .  0.039
        1           . . . .  0 031                0.036               0.041
        1-1/4                0  033               0.039               0.044
        1-1/2                0  035               0. 041              0.049

        2                    0.036                0.044               0.053
        2-1/2       . . . .  0. 039               0.048               0.059
        3                    0.041                0.053               0.065
        3-1/2                0. 044               0.055               0.068
        4          . . . . .  0.045               0.058               0.071
        5                    0  048               0.063               0.079
        g                    0.051                0. 070              0.091
        8      .  ,           0.063               0.088               0.119
        10                   0.079                0. 110              0. 149

        12          . . . .  0. 096               0. 134           .  0. 183
        14  OD               0  116               0. 159              0. 218
        16  OD               0. 138               0. 186              0.254
        18 OD                0. 161               0.214               0.291
        20 OD                0. 189               0.241               0.329
        24  OD  .  ,          o. 210              0. 273              0. 370



         Man hours  include  unloading pipe  from  railroad cars or trucks and placing in shop storage,
     procuring  necessary pipe and materials  to fabricate  spool  piece,  transporting necessary  ma-
     terials to point  of fabrication and the transporting of finished  work to temporary  storage.

         Units apply to any length spool piece or  segment  of work.
   14   15   16   17   18   19   20   21   22   23   24