                            Heavy Wall Carbon Steel Material

                            DIRECT MAN HOURS PER FOOT
        Nominal                     WALL THICKNESS IN INCHES
         Pipe
          Size      .750    1.00   1.25   1.50   1.75   2.00   2.25    2.50
        3 "or less  0.065  0.078    „      ..     ..     ..     „
        4           0.071  0.087  0.103  0.119    -      ..     ..
        5            ..    0.099  0.119  0.139   0.159  0.179   ..     ..
        6            -     0.110  0.129  0.148   0.199  0.218  0.237   ..
        8            -     0.129  0.146  0.174   0.201  0.228  0.255  0.286
         10          -            0.149  0.182   0.215  0.248  0.281  0.314
         12          -      ..      ..   0.214   0.245  0.276  0.308  0.339
         14          ..     ..      ..   0.246   0.274  0.302  0.330  0,359
         16          -      ..      ..           0.284  0.315  0.345  0.377
         18          ..     „       „             „     0.324  0.358  0.392
        20           -      ..                    ..    0.329  0.362  0.405
        22           -      -       „      -             ..     „     0.416
        24           --     --      --            ..            -     0.486
                    2.75   3.00    3.25   3.50   3.75   4.00   4.25    4.50
         10         0.361  0.408    „      ..            ..     „
         12         0.390  0.441  0.498  0.563    -      ..     ..
         14         0.413  0.467  0.528  0.597   0.669  0.743   ..
         16         0.434  0.490  0.554  0.626   0.701  0.778   -
         18         0.451  0.501  0.576  0.651   0.729  0.809   -
        20          0.466  0.527  0.596   0.673  0.754  0.837  0.921  1.022
        22          0.478  0.540  0.610  0.689   0.772  0.857  0.951  1.046
        24          0.494  0.558  0.631  0.713   0.798  0.886  0.983  1.081
                    4.75   5.00    5.25   5.50   5.75   6.00
        20          1.124  1.225  1.323   1.429  1.529  1.636
        22          1.151  1.255  1.355   1.463  1.565  1.675
        24          1.189  1.296  1.400   1.512  1.618  1.731


         Man hours  include  unloading pipe  from  railroad cars or trucks  and placing  in shop storage,
     procuring  necessary pipe  and materials  to fabricate  spool  piece,  transporting  necessary  ma-
     terials  to point of fabrication  and the transporting  of finished work  to temporary storage.


         Units  apply  to any length spool piece  or  segment  of work.