16   Section One-SHOP FABRICATION

                 ATTACHING FLANGES—SLIP-ON TYPE


                               Labor—Slipping on Flange and
                              Machine Welding at Front and Back
                                  Carbon Steel Material

                                 NET MAN HOURS EACH
                                   SERVIC E PRESSURE RATING
         Ins.   150 Lb.  300 Lb.  400 Lb.  600 Lb.  900 Lb.  ISOOLb.  2500 Lb.
                       "                                            r  ~  ~
        2         .66      .72      .96      .96     1.26     1.44  :   1.56
        2-1/2     .78      .90      1.20     1.20     1.56    1.74     1.92
        3         .96     1.08     1.50     1.50     1.86     2.10     2.34
        4        1.26     1.38     1.80     1,98     2.52     2.82     3, ! 2
        6        1.55     1.70     2.25     2.55     3.15     3.55     3.90

        8        1.72     1.84     2.48     2.72     3.32     3.72     4.10
        10       2.12     2.32     3.04     3.76     4.24     4.76     5.24
        12       2.18     2.45     3.26     4.06     4.55     5.11     5.64
        14 OD    2.28     2.55     3.30     4.11     4,80     5.88
        16 OD    2.67     2.88     3.81     4.68     5.10     6.65
        18OD     3.09     3.42     4.40     5.37     6.03     6.75
        20 OD    3.72     4.08     5.37     6.03     6.99     7.83
        24 OD    4.65     5.10     6.51     7.92     8.85     9.90

        26  01)   -       -        7.05     8.58     9.59
        30  01)   _       -        8.14     9.90    11.06     _         -
        34  01)   -       -        9.22     11.22   12.54     -
                                                              _
        :«; OD    -       -        9.76     11.88   13.28               -
        42 OD     -       -       11.39     13.86             -         -
     Man hours include slipping-on carbon steel flange, tack welding and machine submerged arc. Welding both front
     and back. For sizes 2" through 4" time is included for manual welding on front.
     Man hours are for any wall thickness of pipe used with listed flange.
     Above man  hours  should  be used in  lieu of manual welding slip-on  flanged joints on all  shop machine welded
     slip-on flanges which can be rotated.
     Unlisted sizes take the next highest listing.
     For additional information see notes at bottom of preceding page.