Page 69 - Estimators Piping Man Hour Manual
P. 69

52   Section One-SHOP FABRICATION

                MAdHNING INSIDE OF LARGE O.D. PIPE


                                     Built-Up Ends
                                  Carbon Steel Material

                             NET MAN HOURS PER END
                          Machining Inside of Straight  Pipe Only  I.D. Build-Up
                                                                     with
         O.D.               WALL THICKNESS IN INCHES              Weld Metal
         Pipe
         Size     .500 to   1.51 to  2.26 to   3.01 to  4.51 to    Man Hours
        Inches     1.50     2.25      3.00     4.50      6.00       Per End
         26        3.74     4.49      5.35     6.84      8.57        12.88
         28        4.03     4.83      5.75     7.25      9.03        15.24
         30        4.49     5.18      6.15     7.71      9.55        19.26

         32        4.95     5.75      6.50     8.22     10.18        23.58
         34        5.58     6.27      7.13     8.80     10.70        29.67
         36        6.27     7.02      7.76     9.32     11.27        35.31
         38        7.02     7.82      8.63     10.00    11.90        41.40
         40        7.82     8.63      9.55     10.70    12.59        48.36
         42        8.68     9.37     10.47     11.39    13.34        56.70
         44        9.49     10.41    11.39     12.25    14.03        65.67
         46       10.41     11.27    12.36     13.23    14.89        74.00
         48       11.39     12.25    13.28     14.15    15.76        83.43
         54       12.81     13.78    14.94     15.92    17.73        93.86

         60       14.24     15.31    16.60     17.69    19.70       104.29

     Machining:  Man hours  for machining the  inside  of straight  pipe are  for any taper  bore from  10" through  30'
          included angle. For machining the ends of bends add 100% to the above man hours. For counterboring (up
          to  a maximum of 2" in  length),  add  50% to the  above man  hours.  For  machining  to a controlled  "C"
          dimension (as required for power piping critical systems), add 225% to the above man hours.
     Cutting and Beveling: Man hours do not include cutting and beveling. See respective tables for these  charges.
     Built-Up Ends: Man hours for built-up ends are for building up the I.D. of straight pipe, bends or fittings, at  the
          ends with weld metal and grinding where it is necessary for proper fit of backing rings.
   64   65   66   67   68   69   70   71   72   73   74