Page 72 - Estimators Piping Man Hour Manual
P. 72

Section One-SHOP FABRICATION     55

              PREHEATING BUTT WELDS AND ANY TYPE
                             OP FLANGE WELDS
                                     Labor Only

                               Carbon Steel, or Alloy Materials
                               For Temperatures Up To 400 °F.

                                NET MAN HOURS EACH
                                                                      -  -
                 Standard  Extra
                   Pipe   Heavy Pipe           SCHEDULE NUMBERS
         Size    & OD Sizes  & OD Sizes
         Ins.    3/8" Thick  1/2 "Thick  20  30  40  60  80  100  120  140  160
         2         0,2      0.3     ..   ..  0.2  ..   0.3  „    „        0.4
         2-1/2     0.3      0.4     --   --  0.3  --  0.4   --   --       0.5

         3         0.4      0.5          „   0.4  ,.   0,5       ..       0.6
         3-1/2     0.4      0.5     ...  --  0.4  --   0.5       -        0.8
         4         0.5      0.6     --   ..  0.5  --  0.6   ..  0.8       0.8
         5         0.6      0.8     --   -   0.6  -    0.8  ..  0.8  -    0.9
         6         0.7      0.9     ..       0.7  ..  0.9   --  1.1  --   1.3
         8         0.8       1.1   0.8  0.8  0.8  1.1  1.1  1.5  1.6  2.0  2.1
         10         1.1      1.5   1.1  1.1  1.1  1.5  1.7  2.0  2.3  2.8  3.2
         12         1.3      1.7   1.3  1.3  1.6  1.9  2.4  2.8  3.2  3.7  4.5
         1400       1.6      2.1   1.6  1.6  1.9  2.5  3.0  3.7  4.2  4.9  5.6

         16 OD      1.9      2.8   1.9  1.9  2.5  3.2  3.8  4.6  5.1  6.2  7.2
         18 OD     2.2      3.0    2.2  2.6  3.5  4.2  5.1  5.9  6.7  7.2  8.9
         20 OD      2.6      3.5   2.6  3.5  4.4  5.3  6.3  7.4  8.3  9.4  10,9
         24 OD     3.1      4.2    3.1  4.5  5.4  6.6  7.9  8.8  9.9  11.3  12.9

     Pipe  Thickness: The wall thickness of the material  determines the man hours that will apply. For preheating of
          double extra strong material, use Schedule 160 man hours.
     Mitre Welds:  For preheating of mitre welds, add 50% to above man hours.
     Man Hours: Man hours for preheating are additional to charges for welding operations.
     Preheating: For preheating to temperatures  above 400°F. but not exceeding 600°F., add  100% to the  above man
          hours.
   67   68   69   70   71   72   73   74   75   76   77