Section  One-SHOP FABRICATION    59

            PREHEATING        LARGE O.D. 9O° NOZZLE WELDS


                               Carbon Steel, or Alloy Materials
                               For Temperatures Up to 400 °F.

                                NET MAN HOURS EACH
           O.D.                      WALL THICKNESS IN INCHES
           Pipe
           Sizes"     .500   .750   1.00   1.25    1.50   1.75   2.00   2.25


           26          8.2    9.1   10.9   13.2    15.5   17.0   19.5   21.9
           28          8.7    9.7   11.7   14.1    16.3   18.0   20-7   23,5
           30          9.2   10.3   12.5   14.9    17.4   19.3   22.1   25.0
            32         9.8   10.9   13.1   15.7    18.3   20.3   23.3   26.3
           34         10.7   11.7   13.8   16.9    19.7   21.8   24.8   28.3
           36         11.4   12.5   14.8   18.3    21.8   23.9   27.3   30.9
           38         12.1   13.4   16.0   19.5    24.2   26.3   30.1   34.0
           40         13.0   14.4   17.2   20.8    26.9   29.0   33.1   37.4
           42         13.7   15.3   18.5   22.3    28.8   32.0   36.4   41.1
           48         15.7   17.5   21.1   25.5    32.9   36.6   41.6   47.0

           54         17.6   19.7   23.8   28.7    37.0   41.1   46.8   52.8
           60         19.6   21.9   26.4   31.9    41.1   45.7   52.0   58.7
     Pipe  Thickness:  The  size  of the  nozzle  and the  wall thickness of the  header  or nozzle  (whichever is  greater)
          determines the man hours to be used.
     Time:  For reinforced 90° nozzle welds, add 100% to the above man hours.
          For 45 ° nozzle welds, add 50% to the above man hours.
          For reinforced 45 ° nozzle welds, add 150% to the above man hours.
          For preheating to temperatures  above 400°F. but not exceeding 600°F., add 100% to the above man hours.
          Preheatmg  of coupling,  weldolet, threadolet  or socket welds should be charged at the same man hours as
          shown for the same size and schedule nozzle.
          Man hours for preheating  are additional to man hours for welding operations.