Page 81 - Estimators Piping Man Hour Manual
P. 81

64   Section One-SHOP FABRICATION

                       RADIOGRAPHIC INSPECTION
                     X-Ray or Gamma Ray Inspection of Butt Welds

                                  Carbon Steel Material

                                NET MAN HOURS EACH

                                             Wall Thickness    Wall Thickness
           Nominal                            Greater Than      Greater Than
             Pipe          Wall Thickness     Extra Strong    Schedule 120 Thru
             Size         Thru Extra Strong  Thru Schedule 120  Double Extra Strong

            2 or less          0.75               ..               0,98
            3                  0.75               ..               0.98
            4                  0.85              0.98              1.10
            5                  0.93              1.07              1.20
            6                  1.04              1.20              1.36

            8                  1.17              1.34              1.52
            10                 1.31              1.50              1.71
            12                 1.49              1.71              1,94
            14                 1.62              1.86              2.10
            16                 1.81              2.08              2.35
            18                 2.02              2.32              2.62
            20                 2.22              2.56              2.90
            24                 2.74              3.15              3.55


     Man hours listed  above cover radiographic inspection of butt welded joints by X-raying or gamma-ray, at  the
     option of the client.
     For radiographic inspection of mitre butt welds add 50% to above man hours.
     For radiographic inspection of slip-on flange welds add  100% to above man hours.
     For radiographic inspection of nozzle welds add 200% to above man hours.
   76   77   78   79   80   81   82   83   84   85   86