Page 84 - Estimators Piping Man Hour Manual
P. 84

Section Otie-SHOP FABRICATION    67

        MAGNETIC        OR    DYE    PENETKANT         INSPECTION
                          OF   WELDED        JOINTS

                             All  Thicknesses and Schedules

                                 NET MAN HOURS EACH

                          MAGNETIC                        DYE  PENETRANT
       Size
      Inches      Butt  Welds    Nozzle  Welds       Butt  Welds   Nozzle Welds
     2 or  less      0.6            0.9                 0.8             1.3
     2-1/2           0.7             1.1                0.9             1.4
     3               0.8             1.2                1.1             1.6
     3-1/2           0.9             1.4                1.2             1,9

     4               1.1             1.6                1.5             2.2
     5               1.4             2.1                1.9             2.8
     6               1.7             2.6                2.3             3.5
     8               2.0             3.0                2.8             4.1
     10              2.5             3.7                3.3             5.0
     12              3.1             4.7                4.2             6.3
     14  OD          3.4             5.2                4.6             6.9
     16  OD          3.9             5.8                5.2             7.9

     18  OD          4.4             6.6                5.8             8.7
     20 OD           4.8             7.2                6.5             9.7
     24  OD          5.6             8.5                7.5             11.1
     Man hours above are for a single inspection. When specifications call for multiple inspections during the  progress
     of welding, the man hours shown above will apply for each of the total number of inspections.
     Magnetic particle  or liquid penetrant  inspection  of weld end preparations  should be charged at  the  same man
     hours as comparable inspection of the same size butt weld.
     For inspection of reinforced nozzle welds, add 150% to the above man hours to include both the nozzle weld and the
     pad weld.
     For inspection of slip-on flange welds add 50% to the above man hours.
     For inspection of small connections such as couplings, bosses, thredolets and weldolets use the man hours shown
     for corresponding sizes of nozzle welds.
   79   80   81   82   83   84   85   86   87   88   89