Page 90 - Estimators Piping Man Hour Manual
P. 90

Section  One-SHOP FABRICATION    73





     Descaling R. T. J. Flange  Faces: Oxidation (scale) created in R. T. J. grooves  of flanges because
        of  Stress  Relieving  or  Heat  Treating  should  be removed and charged  for  at  the  foEowing
        man hours.

         Flange                                  Flange
          Size              Man                  Size                Man
         Inches             Hours                Inches             Hours
        3 or less            0.6                  14                 2.5

        4                    0.9                  16                 3.2
        6                    1.0                  18                 3.5
        8                    1.3                  20                 3.9
        10                   1.8                  24                 4.6
        12                   1.9
                                                  —                  —
     Miscellaneous  X-Rays:  If specified,  the  following  X-Rays should be taken and charged accord-
        ingly.  Slip-on  Welds  X-rayed will  be  charged  the same  man hours  as  a  Butt Weld X-ray.
        Mitre  and  Nozzle  Welds X-rayed should be charged at  50% more  than  the Butt Weld X-ray
        man  hours.
        Lineal  Welding X-rayed should be charged  at 0.7 man hours per  foot  through 1"  thickness
        and  at  1.0  man  hours  per  foot  for thickness  greater  than  1".  For  alloys add 25% to  these
        man  hours.
     Preheating Coupling  Welds:  On  any  size  you  should  charge  the  man  hours of Preheating  a  2"
        extra  heavy Nozzle Weld.