76   Section  Two-FIELD FABRICATION

       HANDLING        AND     ERECTING       STRAIGHT        RUN    PIPE


                            DIRECT  MAN HOURS  —  PER  FOOT
           Pipe                             SCHEDULE  NUMBERS
           Size
           Inches            10 to  60            80 to  100      120 to  160
           1/4                0.16                 0.17             0.18
           3/8                0.16                 0.17             0.19
           1/2                0.16                 0.18             0.20
           3/4                0.17                 0.19             0.21
           1                  0.17                 0.20             0.23
           1-1/4              0.18                 0.21             0.24
           1-1/2              0.19                 0.22             0.27
           2                  0.20                 0.24             0.29
           2-1/2              0.21                 0.26             0.32
           3                  0.23                 0.28             0.35
           3-1/2              0.24                 0.30             0.38
           4                  0.25                 0.31             0.39
           5                  0.26                 0.34             0.43
           8                  0.28                 0.38             0.50
           8                  0.34                 0.48             0.65

           10                 0.43                  0.60            0,82
           12                 0.52                  0.73             1.00
           1400               0.64                  0.87             1.19
           18  OD             0.75                  1.02             1.39
           18 OD              0.88                  1.17             1.60
           20 OD              1.03                  1.32             1.81
           24 OD              1.15                  1.49             2.04

      Man hours  include all labor  for  unloading and  storing  in yard, loading and hauling to erection
      site, and rigging  and aligning in place.  It does not include welding, bolt-ups, make-ons or  scaf-
      folding.  See respective pages for these items.
       For brass, copper, and everdur pipe, double above man hours.